![]() |
![]() |
|
Site Details ATF Newsletters |
1999 ATF NewslettersMarch | April | May | June | July | August | Sept | Oct | Nov | DecApril 16
In the period since last report we have been busy with PAC99 and the ICFA Meeting on Future Light Sources. As always, many thanks to all contributors to the report. I have added a few names (mostly users) to the distribution list. If any of the newly added addressees would like to receive back issues of this report, please write to me. Ilan Ben-Zvi.
EXPERIMENTS: VISA Magnetic measurements (Reported by George Rakowsky): Undulator Sections #2 and #3 were checked on the pulsed
wire bench. After some adjustments, a satisfactory X and Y trajectory
was obtained in both sections as seen in the image at: VISA_Sections_2_3
(The apparent slope in the trajectory exiting Section #3 is not an error.
In fact, Section #3 is well-matched to Section #4, which is absent from
this measurement.)
Section #1 arrived back from SLAC after rebuilding, with
the prototype laminated gap spacer assemblies replaced with the same one-piece
spacers used in Sections 2, 3 and 4. Next week Section #1 will be remeasured
and retrimmed and will be matched with Section #2. The steering magnets
arrived from UCLA. We are planning to set up four of them on the pulsed
wire bench to calibrate them for Earths field compensation. This
will be done in late April, after completion of the undulator measurements.
Jeff Aspenleiter has completed the automation of R. Rulands
procedure for interferometric measurement of the tooling ball offsets
on VISA. This project included designing and building a control circuit
to interface the DC motor on the straightness interferometer stage to
the computer. He also developed a LabView program for sequencing the positioning
of the stage, reading the interferometer, averaging the readings, and
performing a circle fit to the data to find the true offset of the fiducial.
This will greatly speed up the interferometric calibration of the VISA
magnet sections and the final alignment at the ATF. Good work, Jeff!
A paper on VISA magnetic measurements has been presented
at PAC99.
Following PAC, t============================== rajectory
trimming of Sections #1 and #2 together has been completed. Robert Ruland
was here for three days this week. He brought the rebuilt wire finders
with him. They are now repeatable to <1 microns. We measured the fiducials
of Sections 1 and 2 with the straightness interferometer. Measurements
were done with the magnets in normal and inverted orientation. The repeatability
of measurements at each fiducial appears to be on the order of 5 microns
rms. Robert still has to reduce the data, with reference to the CMM data
from SLAC.
I attended the ICFA Future Light Sources Workshop at Argonne
last week and gave a talk on the VISA undulator. It seemed to have been
well received.
VISA Optics (reported by Alex Murokh):
1. Undulator Probes
The design is completed by Erik Johnson. The first mirror
will be shipped to UCLA for polishing by Monday next week. The complete
prototype will be build at a BNL shop in two weeks. If all goes well all
the probes will be ready in the mid-May Then, the probes will be tested
and connected to the feed-throughs. Hence, if there will be no major drawbacks,
the complete installation of seven diagnostics ports can be performed
in the mid-June.
2. Alignment laser
It is ordered. Initial testing will be done at UCLA (and
maybe SLAC). It can be shipped to BNL in mid-May. The mounting will be
designed by the end of April.
3. YAG optics
The cameras are ordered (Hitachi KP-M3). The choice of
lenses and a complete system layout will be finalized by the end of this
week. All the components should be available for installation in May.
4. FEL light optics
Flippers will be ordered this week. A complete design
will be finalized next week. Will be ready to install at the end of May.
5. Control and data acquisition
The systems above require fair amount of control. The
details will be discussed within next few weeks. Hopefully, the experimental
schedule will stay unaffected, as the control system can be worked out
in parallel with the hardware.
The following items were accomplished during the week
of April 26.1999.
The following is a list of technical accomplishments for
the week of 4/5/99.
The following is a list of technical accomplishments during
the week of 4/12/99.
The cathode of the RF gun was changed to inspect the surface of the old cathode and change to a new cathode. The magnesium cathode taken out of the gun was inspected by Triveni Srinivasan-Rao. We were able to find two craters on the cathode with a diameter of about 100 microns and a depth of 0.0006 inch. Comparing a copper cathode taken out two years ago, the copper cathode has many more craters at depths of about 0.0004 inch. We will start preparing the magnesium cathode which was taken out next week, once we receive the cleaning agent. Photographs of the replaced magnesium cathode and the old copper cathode are shown at atf_cathode The damage conditions are very similar for the two cathodes. We know from previous experiment that no double pulse was observed for the copper cathode. We were be able to operate the ATF RF gun at 24 C today. After 3 hours of conditioning we reached a field of 70 to 80 MV/m. We will resume the conditioning next Monday. We are planning to test the cathode next Tuesday afternoon. CO2 laser (Reported by Igor Pogorelsky):
Modification of the CO2 slicing from 200 ps to 10-7 ps
is under way.
A system of 11 thermocouple was installed to monitor the
temperature in a few locations in the Yag room. The thermocouples were
calibrated to provide identification of temperature fluctuations and variation
from one location to another with an accuracy of about 0.2 degree C. The
system is running and collecting data. The initial data shows fluctuation
in temperature of 1.5 - 2 degrees C (peak-to-peak). More detailed information
will be available next week. That amplitude is in agreement with data
measured by original temperature control system.
New Oscillator Mode Measurement (Reported by Adnan Doyuran):
I measured the beam size at different positions. While
Y kept diverging, X gave a focus after 4m. We made a Gaussian fit to this
beam and found the parameters of the beam using Mathcad. The result is
in a pretty good agreement with the measurement. Then using Beamcad we
calculated the optics and found out that we need a +2m focal length cylindrical
lens for the Y direction and for beam matching we need a -1m lens. These
have been ordered on Thursday.
Laser (Reported by Marcus Babzien):
There has been no laser operation for two weeks due to
the HVAC work on the clean room. The new chiller is now in place, and
ductwork, insulation, HEPA fan controllers, and fireproofing have been
added or modified to continue to improve performance of the HVAC system
and meet safety requirements. The HVAC shutdown progressed enough last
week to allow work to begin in the YAG room. We expect that the climate
control will be better able to prevent high humidity in the room, and
that there has been some reduction in vibration. Temperature monitoring
and vibration measurements will show if these parameters are now within
acceptable limits, but observations so far indicate that they are not
and further effort will be required. Some final work in the ceiling plenum
was completed by Tuesday, and then extensive cleaning was performed to
restore clean room conditions. The electronic equipment previously moved
for the shutdown was reconnected and all cabling restored. Thermocouples
for more careful temperature measurements were installed and are now being
recorded on an additional PC installed in the YAG room. This PC is also
able to recall HVAC data recorded by Plant Engineering.
Preparations for the testing of the new oscillator also began this week. The first test will be to illuminate the photocathode if possible and check the beam quality. To accomplish this quickly, the mode of the output beam was characterized, and mode matching optics purchased. The transport and matching optics are being installed to enable quick changeover between seeding with the old oscillator and the new one. If the new oscillator amplifies well, a test beam may be available as soon as Tuesday afternoon. SCHEDULE (reported by Xijie Wang):
Klystron thermal insulation: John Skaritka presented an
overall outline design of the insulation. The detailed design will be
finished next Friday. Bill Cahill will order parts soon, and John will
arrange a meeting with plant engineering to plan for the installation.
Noise problem. Marc Montemagno suggested that the source
of most of the ATF electromagnetic noise may be the gun klystron power
supply SCR. Vitaly proposed to borrow a power supply from the NSLS to
test if this is true. If so, the ATF should proceed to purchase a new
power supply.
ATF Schedule:
There is a great uncertainty in the ATF schedule due to
the on-going YAG laser work, so the main work next week will be:
Last Modified: December 3, 2007 |
|||||||||