1999 ATF Newsletters

March | April | May | June | July | August | Sept | Oct | Nov | Dec

June 4 | June 11

 

Contents

1. Introduction

 

 

In this (short) week the YAG oscillator came back from CLEO and was

re-installed. We used one day to re-install the oscillator, one day for beam

studies, one day for HGHG and one day for STELLA. The YAG laser stability was exceptional, 1% to 2% rms energy stability in the UV, with outstanding mode and mode stability.

We are still suffering from humidity problems in the YAG room causing change in optical component properties and possible permanent damage. Plant Engineering is working to solve the problem.

Ben Poling and Roger Carr finished a 3 day fruitful stay at BNL, working on the VISA wiggler.

Communiqué from Argonne: Vadim and his wife welcomed a new son to the world on June 2, 1999. His name is Phillip. He weighed 5 pounds and was 47 cm long. He was born at 00:24. Mom and baby are doing well. (So is dad, he is walking on clouds!)

Ilan Ben-Zvi.

Back to Top 

Experiments

 

Magnetic Measurements (Reported by GeorgeRakowsky)

 

VISA:

Roger Carr and Ben Poling, together with the NSLS Surveyors and mechanical technicians, reassembled and aligned the VISA vacuum box. They also began assembling the interferometry rails. Brian Fuss and a SLAC technician will be here next week to finish assembling the alignment system. One steering coil stand had to be modified to clear an interference with the alignment frame.

Lorraine analyzed the 90 and 270 degree fiducial data for VISA Sections 1 & 2 and found that the measurement errors are within the error budget. The main source of error is the fit between the tooling balls and the sockets on the gauge bar, due to wear of the aluminum sockets. We will replace the latter with a harder material.

George and Roger Carr examined the impulse response (proportional to 1st integral of the field) of the pulsed wire in Sections 1 & 2, using a Le Croy scope, which has higher resolution than our HP scope. Roger will use this data to try to determine dB/B and dE/E of the beam.

HGHG:

The tilt limit switch and the vacuum pipe touch switch assemblies are ready, but have not yet been installed. LED’s are being added to indicate an open limit switch, for diagnostic purposes. The hardware will be installed and wired in on Monday.

Back to Top 

HGHG Experiment (Reported by Adnan Doyuran, Vitaly Yakimenko and Xijie Wang)

We had a very good round and stable beam. The charge was 200 pC. We tested

the transition radiation beam profile monitor located in the middle of the modulator wiggler, and got a reasonable beam profile even at this low charge. The trajectory was also very good. When we overlap the HeNe and e beam at monitors 1. and 5. we got a reasonable offset on >the 2nd, 3rd, and 4th monitors. Vertically it was perfect, horizontally was >good. Then We ran Vadim’s trajectory program , vertical with HeNe and >horizontal without HeNe (focusing only), horizontal trajectory got better, as expected. We measured spontaneous radiation from radiator. We got >about 200 mV with 200 pC charge.

For pictures of the beam on the five monitors before the correction,

(electron beam nice small spot, HeNe laser large, ugly spot - we will fix

that), click on

May_4_hghg_monitor_images

Back to Top 

VISA Experiment Progress (Reported by Roger Carr)

Three crates of Robert Ruland’s alignment materials have arrived. Holes in the top plates for the alignment fixtures that were misdrilled will be corrected. Also, the trim coil mounts that were placed inside the alignment fixtures did not fit, and these are being redone.

The vacuum boxes, undulator mounts, pedestals and tables were all re-assembled this week, and surveyed into place. The mid-point flanges in the vacuum box are not perfectly square, so they are about 2 mm higher than the end flanges, and cause the tank to bow up in the center. This should not be a problem; they have all been located in position by the survey crew, and all numbers have been recorded.

There is no way in the previous design to re-locate the midpoint flanges to each other, so ‘Dutch’ pins will be placed between the flanges to facilitate re-location. Roll has been taken out beforehand, to about. 1 milliradian, between the two vacuum tanks.

I would add the comment that it is MUCH easier to work on VISA in building 726 than in ATF, and I hope the system is not placed in ATF pre-maturely. I hope the optical diagnostics and bpm’s and alignment laser systems can be thoroughly debugged in building 726.

 Back to Top 

VISA Matching Section (Reported by X.J. Wang)

 

The quadrupole magnets and stripline beam position monitors were installed. The parts and pre-assembled for four beam profile monitors are now finished, ready to be installed next week. Cameras for the beam profile monitors waiting to be ordered. R. Carr of SLAC is searching 100 MHz peak sensitive ADC to improve the ATF stripline beam position monitor for VISA.

Back to Top 

STELLA Experiment (Reported by Karl Kusche for the STELLA team)

1) Beamline #1 was readied for the beam studies run of this Friday (6/4).

Results of this run will determine if further quad rotation is appropriate. Regardless of the need to further rotate the last triplet, it was realized that no further surveying or machined parts will be necessary for the short-term. Manual rotation, with the help of a borrowed inclinometer, can be accomplished such that each quad is within +/- 1 degree of each other (which is acceptable for now).

2) ICA optical system restoration & realignment continues in preparation for ICA recommissioning during the months of June & July.

The local STELLA group satisfied the following goals during beamline #1 run on 6/4/99:

1) Improve e-beam transport through the ICA gas cell (1x1 mm square windows and 0.6 mm laser shield are limiting apertures; 5-10% of ~200pC total charge was delivered to end of line).

2) Observe beam distribution on spectrometer BPM (end of line); desired vertical line on screen indicates that 45 degree quadrupole rotation is probably OK (will study further next run).

3) Compare YAG single-pulse and double-pulse modes.

4) Operator training.

5) Identify problems (and potential improvements) with imaging, etc.

To be resolved before and during the next run, scheduled for 6/9/99:

  • Maximize beam transport through gas cell, and finalize decision to keep quads at 45 degrees
  • Final radiation survey
  • Correct imaging problems with GPOP4 (off-center with "ghost tail") and cell camera (increase light collection)
  • Correct imaging problem with BPM7 (reduce background light leakage)
  • Prepare striplines (GSL2,3,4)
  • Check OTR signal on GPOP4

 

Back to Top 

Facility

 

Computer Control System (Reported by Bob Malone)

1) Debugging continued on the YAG slow drift energy correction software. A problem was noted where the server program would not respond to an operator request to disable the correction. This occurred around every 1 in 90 times the program was tested. After several days of study, it was traced to a software time delay which did not queue interrupt requests properly. It has been corrected and final off-line testing will continue. 2) Software to access the ATF database from a Mathcad worksheet was tested for the first time with real beam. All basic operations to read and write the database asynchronously have been tested and are working.

Back to Top  

Technical Staff Tasks (reported by Bill Cahill)

During this short week, we reinstalled the new YAG oscillator. Had a problem with the YAG preamplifier temperature interlock. It was found that it had no air intake for circulation. The unit was modified and now seems to be working well. A TV camera was installed on the mezzanine to observe the gun and linac phase. This should reduce the troubleshooting time in case of problems. We tested the RF circulator for the gun klystron. This component will protect the kilowatt amplifier in the event of bark-back from the klystron. It will be installed on Monday. All STELLA discrepancies have been resolved. The trim magnets have been reconfigured, cooling water to the sextupole magnet has been installed, video and zoom lenses are complete. The VISA faraday cup pop-in mirror/lens assembly has been completed and remaining pop-ins will be available for installation next week. Digital thermometers have been installed in the RF gun area, the new klystron enclosure and on the mezzanine. This should help us better control the temperature and avoid unnecessary downtime. An additional a/c unit was installed in the control room to reduce equipment heating.

Back to Top 

 CO2 and YAG Laser Status (Reported by Igor Pogorelsky)

Installation of beam enclosures for the CO2 laser transport line between rooms C1 and C2 and work on eliminating gas leaks in the CO2 laser preamplifier and in the terawatt amplifier are still in progress. The new YAG oscillator is back after exhibition at CLEO 99. There are a couple of new observations that need to be addressed:

1. The output power is 250 mW as compared to 325 mW before the exhibit and 375 mW a month ago.

2. A high sensitivity of mode locking due the parasitic optical reflections from downstream of the oscillator. That results in the 5-10% standard deviation of the energy after preamplifier. The problem has been eliminated after realignment of the end mirror in the oscillator cavity and replacing a polarizing beamsplitter downstream the oscillator. However, there is not a full certainty that the bad behavior is gone forever and is not a transient phenomenon that may repeat itself.

3. Another indication that something is not quit right with the mode-locker is the observed transient phase instability. That appears as periodical several second long jumps by ~1 ps. Sometimes this jumps are not periodical, but still reproducible in length and amplitude. Most of the time phase shows a normal behavior with a slow stabilization drift in response to a change in external conditions (vibration shocks or temperature changes). Thermally stabilized enclosure around the oscillator looks to be necessary to improve the phase stability.

In spite of the mentioned above negative observations, we had a very positive experience most of the time servicing a photocathode with the YAG laser beam. Energy standard deviation at all control points was around 1-2%. Laser profile on photocathode was smooth, quasi-Gaussian and stable within a few micrometers. (I believe that the pointing and energy stability will be reported by X.J.) We shall understand however that the improved stability is partially due to a significant clipping of the central portion of the laser beam by the iris that selects a 3.5:1 ellipse out of the whole laser beam.

We will start to use a total laser beam next week upon installation of a

cylindrical telescope

Back to Top  

Beam Operations (Reported by Xijie Wang)

Following is the brief summary of the ATF operation this week:

1. Tuesday: Marcus , Bob and Igor installed the oscillator and realigned the optics. Amplifier chiller broke down and temporary replacement was installed. No e-beam.

2. Wednesday: Igor got the laser ready at about 12:00 PM, but both laser energy and profile were unstable. Igor traced this to a back reflection which caused oscillator instability. Igor started work on polarizer isolation at about 2:00 PM, and laser was ready at 5:00PM. Both laser profile and energy are very stable shot-by-shot. Laser energy peak-peak varied less than 5%, and rms less than 1%. Laser centroid rms variation less than 1.5 microns, and spot size rms variation less than 1 microns for a 1.5 mm diameter laser spot. We observed laser energy slow drift down about 20% in first hour, Igor increased the voltage of the pre-amp power supply by 1% and the laser energy was restored. Phase jitter between the RF and laser on the order of couple pico-second was observed several times. The RF system was stable during those times, but laser phase meter was not working properly. We spend most time optimizing the e-beam. We found the optimal laser position at about 0.7 mm left, 0.5 mm down, in agreement with May 21 results. The charge was low because half the laser spot is now located out of the cleaned area. For a charge between 250 - 300 PC, we measured the rms emittance less than 2 mm-mrad. No bunch length measurement was done due to jitter. Bob Malone successfully tested the emittance program, and new MATHCAD interface with ATF control system. This new tool will greatly increase the ATF on-line modeling and analysis capability. 3. Thursday: Vitaly and Mark fixed the laser phase meter. We observed periodic laser phase jumps of 0.8 ps (calibration maybe off using the e-beam, this should be about a factor of two larger). Igor thinks this was caused by the oscillator feedback motor. We did a test - by opening the laser enclosure, a laser phase jump was observed. By placing a hand gently on the oscillator we observed a phase drift. This problem should be solved in the week of June 14 when the oscillator will be placed in its new location directly on the optical table and the new temperature stabilized enclosure will be installed. A good laser stability, similar to the previous day, was observed. The HGHG experiment was started at about 11:30 AM. The beam was stable with some small laser phase jitter. We observed the RF gun klystron phase being unstable between 4:00 and 4:30 PM. By 5:30 PM, HGHG finished its task of the day. We prepared to clean the cathode, but laser pre-amp shut down due to water over temperature. We traced the problem to the vestibule temperature rise, caused by AC fan shut down aimed at reducing vibrations. This problem was temporarily solved opening the door to the laser laboratory and increasing the air circulation of the power supply. 4. Friday: 10:30 AM laser was ready with similar good stability in energy and profile, laser phase jump was observed. RF gun klystron phase is not stable between 12:00 and 12:10 PM. Following the Stella run we plan to clean the cathode.

In summary, we have demonstrated this week that both laser and RF systems are stable under hot weather.

Back to Top 

ATF Schedule (Prepared by Xijie Wang)

June 99 schedule

 

Plans for the June 14 ATF mini-shutdown:

a) Install new oscillator in the final position: John and Bill will contact Tom White to make sure the Temperature enclosure is ready, at least bottom part. b) ATF plug door modification for VISA experiment: Concrete blocks will be poured at a roughly similar size. John and Bill will meet the plant Engineering people to finalize details on Monday. c) RF improvement: Mark will test low level and kW RF system during the shutdown. d) Diagnostics work: Install new ion pump and change Lpop1. Bob Harrington has to bake out the screen for Lpop1 (one day). This job will wait if YAG laser jobs require his time.

Back to Top 

 

Top of Page

Last Modified: December 3, 2007
Please forward all questions about this site to: Vitaly Yakimenko