1999 ATF Newsletters

March | April | May | June | July | August | Sept | Oct | Nov | Dec

March 12 | March 19 | March 26

 

Contents

1. Introduction

2. HGHG
 
  

 

We received the report of the Laser Advisory Panel. You may see the report at Report_of_ATF_Laser_Panel

 

Due to a combination of reasons (PAC’99, the 4th Generation Light Source Workshop at Argonne, ATF two week shutdown to install new YAG Clean Room chiller and air conditioning modification) there will be no reports for the next two weeks.

Back to Top

Experiments

 

HGHG

 

Trajectory studies (Reported by Vadim Sajaev)

There was one run this week devoted to the trajectory study. A new algorithm of orbit correction was tried. This method doesn’t use the HeNe laser at all. We vary the main focusing in the Cornell wiggler and measure the relative trajectory change. Analyzing these changes, the focusing axis of the wiggler can be found in both planes. The result of this test was satisfying (exciting!): trajectory in both planes was corrected with accuracy of +-30 micons. It works better then the previous method which relied on the HeNe laser, probably due to problem with HeNe images in pop-in monitors. The images are still poor, even after change of the mirrors.

Back to Top

Optics (reported by Adnan Doyuran)

This week on Monday I checked the He-Ne positions on the wiggler pop-ins. During the run we need to shift the beam with a thick glass, in the x and y directions. In that case beam was clipping on the right side of the mirrors at pop-ins 1, 3, and 4.. Monday and Wednesday Erik and I spent some time to align the beam on the left central side of the mirrors because we’ll be shifting the beam to the right.

Back to Top

Compton (reported by )

The Compton experiment ran two days, Tuesday and Friday. A search for a signal is in progress.

Facility

 

Back to Top

Technical staff tasks (reported by Bill Cahill)

1. Design periscope for new YAG oscillator.

2. Modify internal components for Compton Experiment.

3. Evaluate new gun cathode for possible trapped air chamber.

4. Terminated Heliax cable for joule meter readout.

5. Investigated phase jitter in linac rf system.

6. Researched and ordered components for linac water servo system.

7. Completed new phosphorus screen for LPOP1.

8. Completed assembly for HPOP1.5.

 

Back to Top

Computer & Control System (Reported by Bob Malone)

Facility:

Orders have been placed for components needed to build a duplicate frame grabber system and to improve the performance of the existing one. The new frame grabber will be based on a 400 MHz Pentium II motherboard with 128 MB memory. The present system will be upgraded from its 133 MHz processor/64 MB memory to match the new one. Both systems will have the same operator interface and network control capabilities and will be able to operate independently. Design changes for database and network servers needed to support both machine are almost complete.

Expected arrival date for the new hardware is near the end of April with deployment several weeks later.

YAG laser support:

A YAG laser camera scan was set up March 25 and allowed to run overnight. Statistics from 18,100 video frames (4525 frames at 4 locations) were captured and recorded. This information will provide a base line for before/after comparisons once work on the YAG climate control has been completed.

Back to Top

YAG system (Reported by Marcus Babzien)

Over the previous weekend the YAG oscillator shut down on internal interlock. The cause was eventually traced to a bad contact in the umbilical between the controller and laser head. By the time this had been corrected it was too late for any running on Monday, and a water leak had opened up in the oscillator cooling loop. This was repaired Tuesday morning, the system was realigned, and operated the rest of the day.

The new demo oscillator from Time Bandwidth Products was received on Tuesday, and a quick check was performed to confirm no major damage was suffered in shipping. Preparations were begun for testing the unit after the HVAC shutdown next week.

Wednesday morning some time was made available from the HGHG run to perform laser measurements in the gun hutch. Specifically, the gun entrance window was visually inspected for fluorescence under illumination with UV from the YAG system, and no emission was observed. Second, the back reflections from the two surfaces of the window were found and the energy in these reflections measured. Relative to the incident beam, approximately 3% reflects from each surface, which is close to the 4% expected. Together, these measurements show no evidence of suspected damage to the entrance window, and any double reflections in the forward direction should be negligible. Other measurements with an improved dynamic range photodiode showed that the pre-pulse arriving at the gun from the residual CO2 slicing pulse is down 3000 times relative to the main pulse. Post-pulses where not observed above a noise level of 1% out to ~50 ns after the main pulse.

Thursday the system was down for maintenance and preparation for the upcoming shutdown and oscillator testing. Last night additional cameras were installed to monitor oscillator pointing stability, and beam position was measured overnight. Beam motion was observed directly out of the oscillator, which was correlated with drifting temperature on the table, and was the dominant component of downstream beam deviation into the amplifiers.

Friday the laser was operated for the Compton experiment, and final work plans for the shutdown were addressed.

 

Back to Top

Schedule (reported by Xijie Wang)

 

Week of March 29, 1999

PAC 99, Monday through Friday

Mon-Friday

YAG room chiller installation, Babzien and Cahill.

Klystron insulation, Cahill.

Friday, April 2, 1999

ATF Clean up for PAC 99 tour: Cahill

Saturday, April 3, 1999.

12;00 PM - 3:00 PM, PAC 99 tour, Wang, Yakimenko, Pogorelsky, Kusche,

Malone,Yu

Week of April 5, 1999

Monday - Friday: ATF Chiller/HVAC work and Klystron insulation.

1. Remove wakefield experiment.

2. Reinstall Stella spectrometer.

3. Install new laser port window for the RF gun and new cathode (if

components are ready).

4. Test of new laser oscillator.

Back to Top

 

 

Top of Page

Last Modified: December 3, 2007
Please forward all questions about this site to: Vitaly Yakimenko