1999 ATF Newsletters

March | April | May | June | July | August | Sept | Oct | Nov | Dec

November 5 | November 12 | November 19

 

Contents

1. Introduction

 
   

 

Greetings to all,

This week we held the VISA Collaboration Meeting. It was a very good meeting. The previous VISA meeting at BNL took place on January 1998. We had many video conferences in the meantime as well as in-person meeting at SLAC and UCLA, but this time seeing the advanced state of the various systems at BNL was invigorating. We are all looking forward to the installation of the VISA undulator at the ATF which will start in a little over one week.

 A photograph of a small (and pleased) group of participants can be seen next to an undulator section being measured at the NSLS Magnetic Measurements Laboratory. Left to right: Jeff Aspenleiter (BNL), Art Toor (LLNL), IBZ (BNL), Claudio Pellegrini (UCLA), George Rakowsky (BNL) and Vitaly Yakimenko (BNL). The picture was taken by Max Cornacchia, (SLAC):

 11_5_VISA_mtg

 Ilan Ben-Zvi.

Back to Top   

STELLA Experiment (REPORTED BY KARL KUSCHE)

1)   Beamline #1 preparations for the runs this week were completed, including installation of a new CTR foil (0.25 mil Al) at GPOP4.  Vacuum, leak check, and survey of the line were accomplished.

2)   Vitaly utilized the first run (Thursday) to deliver ~100% of ~0.5nC at 45 MeV through the new STI wiggler to the spectrometer.  Remember that the ICA gas cell is *not* installed at this time.  A radiation survey was performed, giving approval to the restacked shielding at the end of the line.  After the tune was improved, it was observed that the new wiggler (permanent magnet) does not cause detectable steering to the beam.

3)   The rest of Thursday afternoon, as well as most of Friday, was spent aligning a HeNe laser beam through the wiggler.  A problem with the positions of some of the beam profile monitors was discovered, with respect to the beam axis.  The group decided that the next step for beamline #1 will be to bleed it up to nitrogen and carefully realign all diagnostics (and the wiggler bore, if necessary) to the HeNe beam axis, after its overlap with the e-beam axis has been verified.  The next few weeks of ATF shutdown will provide a fortunate opportunity for this alignment work.  Delivery of the GW CO2 will follow.

4)   Progress at STI Optronics:  The ICA gas cell internal BPM has been redesigned and fabricated, which will be used to visualize the overlap of the CO2 laser and electron beams.  It consists of a VOx chip on a finger which is mounted onto a translation stage.  Accommodations for alignment and heating of the VOx (necessary to visualize the CO2 profile) are included.  STI is now preparing to test the VOx with a CW CO2 laser.  They have also effected repairs on the encoder mike controller (gas cell laser mirror alignment), which failed during our last week of running in August.

Back to Top

VISA Experiment (REPORTED BY AARON TREMAINE)

A valve can be installed before the VISA undulator which will isolate VISA from the rest of the experimental hall beamlines.  Vacuum testing on the chamber was done with a single 240l/s pump. With no magnets, the pressure at the far end of the chamber  (with respect to the turbo) was in the 10^-6 range after 6 hours of pumping. Tests were done with one and two sections and after pumping for 2 days with 2 magnet sections inside the chamber, a pressure at the far end of low 10^-5 was measured. We believe with better conductance and another turbo, when all four sections are installed, we will be able to get to the desired pressure for the ion pumps to kick in.

Robert is coming Nov. 8 and next week will test out the alignment system on all four sections of undulator.

In addition, we need to mechanically test the BPM pop-in assemblies. A long term solution for checking the BPMs when inserted has been found. By electrically isolating the pop-in from the chamber, a simple ohm-meter will tell us if contact has been made between the pop-in and undulator.

XJ has agreed to run beamline 3 before the installation starting Nov.15.  We need to assemble a working BPM with optics and install it in the beamline no later than Wed. (Nov. 10) of next week.

There were near term solutions for the BPM mirrors that were discussed at the meeting earlier this week.  Hand polishing the mirrors will be tried as soon as the holder assembly from UCLA arrives. It was FED EXed yesterday.

This will give us around 2 lambda. We are waiting for the lamda/2 mirrors to arrive. Then the will be glued to the BPM side mirror and the better of the two will be pursued for the BPM test next week.

Back to Top  

VISA Magnetic Measurements (REPORTED BY GEORGE RAKOWSKY)

 

VISA sections 3 and 4, as well as both wire finders, have been measured on BNL’s CMM. Sections 1 and 2 are being measured tonight (Friday, 11/5/99). The accuracy of this machine is 0.0002” (5 um).

The biggest discrepancy with SLAC CMM data is in the wire finders - about 0.006” (150 um)! Discrepancies in the measurements of Sections 2 and 3 are much smaller. BNL’s CMM measurements agree with Jeff’s micrometer measurements to within 0.0002”. Closure errors for Section 3 in 0 and 180 degree orientations are now in the acceptable range. I believe we have found the smoking gun, although we have not figured out who pulled the trigger. We can always blame Federal Express, I suppose.

At this point, we have completed fiducialization on Sections 2 and 3, and Sections 1 and 2. Section 3 has been installed in the vacuum vessel with two pop-in assemblies in place. Sections 1, 2 and 4 will be installed Monday, in preparation for the alignment exercise. We will have the latest fiducial data for Sections 1, 2 and 3 available for Robert. For Section 4 we can use old data, just for the exercise. When the alignment, pop-in fitting and other dress rehearsals are done, we will take Sections 3 and 4 back to the Magnetic Measurement Lab to complete the fiducialization, as per Aaron’s plan.

Back to Top  

YAG Laser (REPORTED BY MARCUS BABZIEN)

This Monday’s scheduled laser maintenance was realigned of the oscillator, again because of degradation of the saturable absorber.  Although this problem last occurred in August, the process is the same.  The high intracavity power slowly causes a decrease in reflectivity of the saturable absorber, and after large enough loss develops, mode-locking is affected.  The solution tried in August was to reduce the pump power and compensate with higher gain in the amplifiers.  However, this appears only to have increased the decay time, and further decreases in pump power would not only require higher amplifier gain, but also start to affect mode locking and beam profile.  Periodic realignment works temporarily because the active region of the saturable absorber is much larger than the mode size, and the beam can simply be repositioned to an undamaged area.  The new oscillator being built will incorporate a higher damage threshold saturable absorber and larger mode size for much higher resistance to this problem.

Otherwise the system operated uninterrupted throughout the rest of the week.

Back to Top 

Technical Operations (REPORTED BY BILL CAHILL)

Due to various illnesses and absentees, this weeks workload was not as productive as anticipated. Most of the time was spent investigating and purchasing needed equipment for the ATF. New HV power supplies for the rf modulators, the temperature controller for the I/Q modulator system, additional pop-up solenoid valves for diagnostics and ion pump “holding” power supplies for the facility vacuum system. The new quadrupole in beamline #3 was wired and assigned to the computer system. Marc has re-certified himself in “Hazardous Waste Generator” training and I have re-certified myself for “Laser Safety Training”.  Mechanically, Bob has been working with Igor, addressing the needs of the CO2 laser system. He is also fabricating a phosphor screen for the VISA Experiment. Missing parts were found relating to the Visa project.  The reorder was canceled and much time and money have been saved. A large effort was spent assisting our Russian experimenters setting up their equipment for the BPM experiment in the ATF tunnel. A delay in the installation of the stripline receivers for the VISA experiment. NSLS electronic support has been delayed due to conflicting job assignments.  We will begin assembly of two units immediately and are negotiating the completion of the remaining units with NSLS at the earliest possible opportunity.

Back to Top

 

Top of Page

Last Modified: December 3, 2007
Please forward all questions about this site to: Vitaly Yakimenko