1999 ATF Newsletters

March | April | May | June | July | August | Sept | Oct | Nov | Dec

November 5 | November 12 | November 19

 

Contents

1. Introduction

3. STELLA
4. VISA
 

 

Greetings to all,

The study of BPM screens for the purpose of VISA was completed weeks ago, but we have a nice set of transparencies presented by Alex Murokh at the UCLA Workshop:

11_19_YAG

Two interesting items this week. The Beam Position Monitors for Linear Colliders experiment, led by Vladimir Balakin, had another successful run, reported below. The Russian group at the ATF can be seen at: 

BPM group 11_99 

The big move is here! The VISA undulator vacuum chamber is being installed at the ATF. At the same time the magnetic measurements of the undulator steering magnets were done.

The work on the STELLA experiment continues diligently:

11_19_STELLA - Karl

Ilan Ben-Zvi.

Back to Top 

BPM for Linear Colliders (REPORTED BY VITALY YAKIMENKO)

 

Progress in the Linear Collider development requires methods to measure beam position with extremely high precision. The device consisting of three RF cavities was installed at ATF beam line to investigate limitations for the BPM resolution. This week run was continuation of the series of runs and resolution of 250 nm online and 150 nm filtered achieved during last run at the end of 1998. The goals of this run were: check resolution at high electronic sensitivity compare to previous run. The position jitters were limiting factors for the electronics sensitivity during previous runs. Improved position and phase stability of the ATF electron beam allowed using high sensitivity range. Increased sensitivity does not translate into improved accuracy automatically. Noise level and non-linearity of the electronics (due to reduction in the dynamic range) was amplified by increased sensitivity.  check possibility to use additional cavity to generate reference phase by electron beam instead of special signal from ATF RF system that can introduce RF phase jitters and drifts.

Online accuracy of 200 nm with reference line and 150 nm with internal phase generation were achieved. Accuracy will be further improved by taking into account the non-linearity of the electronics during “home analysis”. The results of this run prove that the phase jitters from external reference produce considerable contribution into resolution. The resolution test, showing a preliminary resolution or 150 nm, can be seen at:

11_19_BPM_meas.

Other possible limitations in this experiment for the beam position measurement appear to be related to the electron beam tails or satellites.  RF signal analysis suggests electron beam satellites separated by 10-12 ns from main beam and amplitude of couple percents. This can be seen at: 

11_19_BPM_dpuls  

Thus the BPM equipment serves also as a large dynamic range longitudinal charge diagnostic.

Back to Top 

STELLA Experiment (REPORTED BY KARL KUSCHE)

 

Beamline #1 spectrometer has been removed to allow for HeNe line-of-sight from GPOP1 mirror to end of Experimental Hall.  This will permit alignment of all BPM’s and direct inspection of the dipole bellows.  The large diameter spool piece upstream of triplet #2 has been removed for machining to allow for the installation of an additional gate valve for vacuum isolation of GPOP1 assembly.

Back to Top 

VISA Experiment (REPORTED BY AARON TREMAINE)

Ben arrived and the vacuum chamber has been installed in the ATF and rough surveyed into place, as can be seen: 11_19_VISA_und.  

The alignment rails (for the laser interferometer) were put up today. Also, the vacuum group is preparing the chamber and connecting the chamber with the spool pieces to the four ion pumps. See: 11_19_VISA_und2.  

Once this is done, the system will be turbo pumped, baked, and leak checked.  Pictures of the system and people will be posted on the web thanks to BNL crack field photographer, Ilan.

There are two solutions for the BPM mirrors. To glue lambda/2 mirrors onto already existing copper mirrors.  The mirrors have been ordered and should arrive by next Wed. Hopefully the holiday won’t slow down the arrival.  Silicon mirrors are being polished (lambda/10) at Livermore and Art is hoping to have them ready for the final assebly alignment  (around Dec.  1).  When mechanical tests were done, the mirrors/pop-ins could be inserted and retracted without making contact with the magnets. This was a tight squeeze and the FEL side mirror has been reduced from 3.5mm to 3.1mm which we believe will help with insertion/extraction process when at the ATF. We can’t allow the pop-ins to touch the magnets or else the alignment can possibly be thrown off.

Magnet sections 1&2 are done and George and Jeff will finsih with sections 3&4. It would be good at Tuesdays video conference to have the final pulse wire data presented.

I believe we need to take a closer look at the test run of the BPM that XJ and otheres did (results are in last fridays ATF report and pictures are posted on the web) and have discussions on what the results of the TR and Phosphor mean for VISA.

The VISA cable pull was done and termination will start next week.

Schedule Week of:

Nov. 15  Move vacuum chamber assembly to ATF

Nov. 22  Vacuum test chamber, ion pumps, bake-out in ATF, Cable termination

for controls and power

Nov. 29  Magnet characterization for all 4 magnet sections completed

Final design and assembly of BPMs

Robert and team arrives Nov. 30

to align magnets in ATF (final alignment)

Final alignment with BPM insertion will happen the weekend of Dec.3-5. We will only have a few days and so it is important not to dily-daly and get it done lickity-split.

After the final alignment, we can begin to pump down and finish all the cable terminations and controls. Also, the long range transport optics and mounts should be here and can be installed. We still need to redhead the ceiling and mount pvc pipe.

Back to Top

VISA Magnetic Measurements (REPORTED BY GEORGE RAKOWSKY)

 

VISA Sections 3 and 4 are on the bench, ready for tuning and fiducialization.

This week we have been trying to calibrate the VISA Steering Magnets. We set up four steering magnets on the pulsed wire bench, spaced 49.5 cm on center, as specified. The Helmholtz coils were shortened to leave the nominal 2 meters covered by the steering coils free. The idea was to calibrate the steering coils to cancel Earth’s field.

First, the unpowered coils, “out of the box”, produced random trajectory kicks of a magnitude comparable to the VISA magnets before shimming, just due to residual fields, which were several gauss. We then attempted to degauss each steering magnet by applying reverse excitation to the By coils and observing By at the surface of the corresponding pole with a Hall probe.  (We used a Kepco bipolar PS, since the steering coil supplies are all at the ATF.) We were able, by trial-and-error, to reduce the By residual fields below 1 gauss in all four magnets. We then powered all four magnets in series (for By) to obtain a straight X-trajectory. To compensate Earth’s field required only 2.4 mA (yes, milliamps.) Note that the power supplies are rated for +/- 8 amps.  Steering corrections, if any, will be of about the same magnitude. As expected, these magnets have far more capacity than needed, and they need to be degaussed very carefully.  Just for fun, we wound 12-turn windings on each leg of the steering magnets, on top of the UCLA windings. Powering them in series for By field produced cancellation of Earth’s field with about 700 mA. (The current ratio 700/2.4 does not match the turns ratio. Perhaps the 12-turn windings have a lot more leakage than the UCLA windings.) Nevertheless, these windings have adequate range for trajectory correction, and the current is not down in the noisy, lowest-few-bits region of the DAC.

We repeated the degaussing procedure using the Bx windings and monitoring the surface fields at the Bx poles. But, checking the By poles, we found they had acquired residual fields as high as 6.5 gauss, obliterating the degaussing we had done previously on the By poles. This is not surprising, since By and Bx fields share the same iron and affect each other’s history.  This method of degaussing did not seem to work.  Suggestions are welcome.  The traditional degaussing method is to drive the iron into saturation and then cycle the excitation with gradually diminishing excursions until a degaussed state is reached. The iron cannot be saturated with the existing supplies if the field has to cross the large air gap.  However, by connecting the UCLA windings in series aiding, so the flux circulates around the “picture frame” core, the iron can be saturated.  We tried this with one magnet. We opened one joint to create a small air gap, where we inserted a Hall probe. B(core)) reached only 6 kG, because of the air gap and because the Kepco reached its voltage limit.  Nevertheless, we cycled the Kepco with a LabView-generated, decreasing-amplitude sine function. Upon completion of the procedure, the surface fields on all four poles were <0.3 gauss. It may be possible, then, to use the UCLA windings, in series-aiding, for degaussing, and additional, few-turns windings for steering.  For comparison, we tried a pair of rectangular, air-core coils with similar geometry: 6 X 21.5 cm aperture, 2 X 2 cm cross-section, with 81 turns of #18 wire, spaced about the same distance as the pole-to-pole distance in the steering magnets. 2 amps in the air coils produced the same deflection as 3 amps in our 12-turn windings on the steering magnets. It’s an option.

Back to Top

ATF Mechanical Engineering (REPORTED BY JOHN SKARITKA)

 

Stella Activities:

1. The spectrometer on beam line # 1 was moved off it’s surface table.  2.  A 4.5 “ flanged spool was modified to allow for the installation of an isolation valve in beamline # 1.The spool was cleaned, leak checked, and baked.

HGHG activities:

1. New pneumatic actuators arrived this week and were installed into a shutter for the CO2 beam.

2.All the covers required to enclose the CO2 beam to the HGHG experiment have been fabricated. Two sections have been installed, the rest will be installed next week after threaded inserts are put into the ceiling.

VISA activities:

1.   The VISA table , and vacuum vessel was prepared for shipment  and installed on schedule into the ATF experimental hall. The vessel assembly was surveyed that same day.

2.   Prior to the installation of the VISA vessel the Faraday cup/SASI out-coupler mirror assembly was removed from the ATF modified, pre-surveyed , and resurveyed onto beamline # 3.

3.   The VISA vacuum vessel components are currently being assembled and being made ready for pre-baking

 

Terawatt Laser activities:

1.   A preliminary mechanical engineering inspection of the laser amplifier pressure vessel took place last week, and the review process is proceeding.

2.   Work was started up again on needed modification to the laser window safety exhaust tube and the bread board enclosure.

Back to Top 

 Computer Control System (REPORTED BY ROBERT MALONE)

Intensive testing of the new Vista software under Linux continues.  In particular, a key problem with software interrupts and inter-process communication via reliable signals has been resolved.  The problem manifested itself when changes in the test database did not always generate a software interrupt in the associated server process.  This “works most of the time” type of problem is especially tricky to isolate and understand.  Building new reliable and robust servers requires that software (and eventually hardware) be able to generate and service interrupts consistently and dependably over many iterations spanning long periods of time.  The fix merely requires each of our servers to cache a copy of its parent process id for the interrupt handlers to use when rasing a signal.  A small fix, but one with important impact.  Testing of the new method has uncovered no problems in 72 hours of continuous operation.  Software porting efforts can now continue.

Back to Top 

Technical Operations (REPORTED BY BILL CAHILL)

Monday was the start of the experiment hall shutdown. During this time we provided technical assistance to the Russian BPM experiment in the 0* line including operations and tech support. Time was spent on improving camera optics in the laser gun hutch but it was found to create a large heat load and the original camera had to be reinstalled. Technical assistance was also given to the Smith-Purcell Experiment repairing electronics needed for diagnostics. The master oscillator spare was sent out for repair and parts were ordered to build the interface chassis from CAMAC to the VISA pop-ins.  The experiment hall was prepared for the arrival of the VISA wiggler including the removal of all shielding, cabinets and survey stands not needed. We are currently preparing the new Darlington transistor power supply chiller for installation. The design work for the new linac water system is ongoing. Mechanically, assistance was given to installing the CO2 shutter between the amp. and pre-amp room. Unfortunately, the interlock system has not been certified and time has been spent investigating alternative procedures. The fast detector group has requested a cable pull from NSLS electricians but we are still waiting for a response and conformation on a starting date.

Back to Top

The ATF Engineering Meeting (REPORTED BY XIJIE WANG)

 

1.   ATF laser safety: All person must follow laser safety procedure, particularly for laser goggles, they must be certified. Marcus will follow through the purchase order for the goggles.  John was asked to install the laser cover in the experimental hall ASAP, over time is granted for next week. ATF TW CO2 room will be put under administrative control for HGHG laser work, if your name not on the list, please leave the room if room is interlocked for laser work.

2.   ATF Schedule: Next Monday will be used for laser interlock certification, Marcus, Igor and with help from Bill Cahill if needed. During the laser interlock check, you can continue work inside the room, but must stay there until permitted to leave.   Tuesday will be for trajectories studies and feedback test by Vitally. Wednesday will be used for maintenance, Bill will see whether we can install magnet power chiller. HGHG request to switch two days running time in the week of January 10 to other week, we will try to accommodate that in the February. Marcus is asked to operate the CO2 laser for HGHG experiment.  Monday, Nov. 29, we will try to improve the gun water system and install coil. (Harrington, Wang)

3.   YAG laser diagnostics: we need improve the laser image on the monument, and laser energy measurement. Trigger for the Joulemeter is required, Marcus will purchase the parts after the laser interlock check.

4.   VISA experiment: The ATF is in the process of installing the VISA undulator. We request all ATF staff and its users not to use the experimental hall as passageway to the FEL and CO2 room.  VISA is granted exclusive access to the experimental from Thursday Dec.2 9:00 PM to the 1:00 PM of Tuesday, Dec,7, 1999. During those times, the ATF will implement special procedure for experimental hall access, if you need access to the experimental during those time, please contact VISA manager Aaron at X2505.  Pedro will start terminating the VISA cable next week.

5.   Cahill will check the flow of the linac water system, and Mark should start order the more powerful pump if flow is the problem. Mark will finish up the BPM amplifier, and start work on the power supply for HeNe laser shutter.

6.   Harrington will continue work on the CO2 laser, and install Smith-Purcell pump control box on Tuesday.

 Back to Top

Top of Page

Last Modified: December 3, 2007
Please forward all questions about this site to: Vitaly Yakimenko