1999 ATF Newsletters

March | April | May | June | July | August | Sept | Oct | Nov | Dec

October 1 | October 8 | October 15 | October 22 | October 29

 

Contents

1. Introduction

 
   

Greetings to all,

This week we got a bit time to do a few beam measurements, the results are in an HTML file. The measurements, done without significant compression, show beam parameters that are close to what is required by VISA.

The HGHG Experiment concentrated on getting the autocorrelator going for a pulse length measurement.

STELLA has passed beam through the new wiggler and the transmission is good.

Next week we will host a VISA Collaboration meeting at BNL. The meeting will take place at the NSLS Seminar Room. The tentative agenda is:

Monday, November 1, Morning:

09:00 Overview of VISA status, A. Tremaine

10:00  Presentation of undulator status, magnetic measurements, alignment, pre-installation, G. Rakowsky

11:00 Presentation of linac status, matching beam line, beam measurements TBD

12:00 Lunch

Afternoon

01:00 Presentation of status of undulator diagnostics, E. Johnson, A. Murokh

02:00 Status of optical diagnostics, and FEL measurements, J. Rosenzweig

03:00 Visit to ATF and magnetic measurement laboratory.

05:00 Executive committee meeting.

 

Tuesday, November 2, Morning

09:00 Installation schedule, J. Skaritka

10:00 General group discussion

11:00 Executive Committee meeting

12:00 End of meeting 

Ilan Ben-Zvi.

Back to Top

STELLA Experiment (REPORTED BY KARL KUSCHE)

The new STI wiggler had its first day of e-beam delivered through it this week.  Vitaly reports close to 100% transmission of ~0.5nC, with non-optimized beam tune.  There was no obvious clipping or distortion of the transmitted beam.

The first week in November will see two days of continued running to optimize the beam tune through the wiggler.  Coalignment with the GPOP1 HeNe and spot size determination are expected.  Delivery of beam to the spectrometer will be possible after reinstallation of the CTR diagnostic (0.25 mil Aluminum foil replaced) and pumpdown of section #4.

During November & December, it is planned to perform CO2 alignment and transmission optimization with the goal of reestablishing bunching at the CTR diagnostic.  The ICA gas cell will probably not return to ATF before the new year.

Back to Top

VISA Experiment

VISA STATUS AND SCHEDULE (REPORTED BY AARON TREMAINE):

Mirrors (for the diagnostic pop-ins) received from Opticraft ended up being no good... not even for the electron beam diagnostic. Currently, pop-ins made of silicon are being machined and will be sent off for polishing.

Next week (Nov.1) we will start mechanical testing of the pop-in diagnostics in the pre-assembly area. Full assembly of the pop-ins will be done and will be tested on the undulator sections not being measured by George (probably sections 3&4).

John is not here today and results of the vacuum tests done this week  will be reported next week upon his return.

Agenda for VISA:

This is what the schedule looks like for the next 3 weeks:

Nov.1 Test pop-in assemblies, vacuum

VISA collaboration meeting Nov.1&2

Nov.8 Robert and Brian to trial alignment

Nov.15 Move to ATF

VISA MAGNETIC MEASUREMENTS (REPORTED BY GEORGE RAKOWSKY):

We have completed measurements on Sections 2 and 3, including at 90 degrees. We have set up Sections 1 and 2 on the bench and are beginning to align the magnetic axis. To clear up the closure error issue, we have made arrangements with our CMM inspector to remeasure Sections 2 and 3, as well as the wire finders. (He has been tied up on another project the past couple of days.) Measurements with calipers indicate the wire finder calibrations may be off by several mils as well, thereby introducing systematic errors in all the fiducializations. Using the caliper measurements, closure error is about half. Robert Ruland is suggesting that perhaps the epoxy which bonds the tooling balls to their studs has shrunk since the CMM calibration at SLAC.

Back to Top

Beam Measurements(REPORTED BY VITALY YAKIMENKO)

 

Various measurements done in the previous weeks provided good emittance / peak current results, with the best being 1 mm-mrad at 125 amperes. This week we preformed a few measurements at slightly higher peak currents, yet without attempting a significant compression. Marcus Babzien provided various laser settings and measurements. The results are peak currents over 150 amperes at emittance bellow 2 mm-mrad. Some of the measurements results can be viewed in the HTML file:

Beam_Study

Back to Top

YAG Laser (REPORTED BY MARCUS BABZIEN)

There was laser maintenance on Monday during which the amplitude instability from ground motion was further studied.  Inside the room, walking around the table causes 3-5% percent fluctuations.  Outside the room however, the fluctuations are much lower and not measurable above background fluctuation of about 0.5%.

The system operated the rest of the week for tomographgy and beam studies.  Today the effect of the the time slew correction for oblique incidence on the cathode was tested.  By interchanging a mirror and grating, the charge vs. phase curves for three small horizontally displaced beams could be compared with and without correction.  The curves taken with the mirror (no correction) showed very close to the expected 6 ps delay across 2 mm on the cathode.  A second check was to steer a single small beam across 2 mm on the cathode, again producing 6 ps relative delay.  When the grating was used for correction, the delay was less than 1.5 ps, close to the measurement error.

The system required CW realignment Wednesday because of poor amplitude stability, which was restored to 2% rms at the cathode.  The system was last aligned more than three weeks ago.

Back to Top

Technical Operations (REPORTED BY BILL CAHILL)

On the Monday maintenance day, we anticipated finding a defective capacitor in the gun modulator. It turned out to be a carbonized cable to the charging resistor on the PFN. The cable was cleaned and the modulator is running well. The particulate filter for the klystron water system was replaced. This filter was so clogged, it was slowing down the flow. Periodic maintenance will have to be increased to reduce this problem. The mother power supplies for the Darlington transistor network were reconfigured for optimal output. The lead shielding for the STELLA faraday cup was rebuilt and a radiation fault test was performed. The electrical service for the FEL room was completed. This will allow all components to be permanently installed below the optic table. “finally”.  Mechanically speaking, we assisted the CPOD experiment with vacuum expertise. The Plexiglas optical shield was installed on the ceiling between the CO2 room and the STELLA table, the terawatt blow-off pipe was disassembled for modification work. The plasma shutter for the CO2 pre-amplifier is complete as is the machining of the stands for the CO2 amplifier breadboard assembly. All in all, a very busy week.

Back to Top

 

Top of Page

Last Modified: December 3, 2007
Please forward all questions about this site to: Vitaly Yakimenko