1999 ATF Newsletters

March | April | May | June | July | August | Sept | Oct | Nov | Dec

September 3 | September 10 | September 17

 

Contents

1. Introduction

 
 

All,

The main result of this week is success with the Compton experiment (short for Study of Compton Scattering of Picosecond Electron and CO2 Beams). This experiment, carried out with the support of the Japan-US Collaboration in High Energy Physics is motivated by a plan to generate polarized positrons for the Japan Linear Collider. Other applications for high-brightness picosecond and sub-picosecond hard x-rays abound.

Ilan Ben-Zvi.

Back to Top

Compton Experiment (Reported by Igor Pogorelsky)

The 3-day Compton run planned for this week was shortened to cumulative two full days due to hurricane Floyd (BNL was closed at 3 p.m. on Thursday) and morning and afternoon meetings on Friday. Nevertheless, the run objectives have been accomplished. This included: to establish spatial and temporal overlap of the electron and laser beams and to observe Compton x-rays; in addition, spectral content of the x-ray signal has been verified.

  • Spatial overlap has been established by focusing the electron and CO2 laser beams on the 2-mil pop-in fiber cross.
  • Spectral overlap has been established by adjusting the optical delay line and optimizing the x-ray signal on the Si diode.
  • By better tuning of the e-beam the background signal on the Si detector has been reduced to 20 mV.
  • The maximum Compton signal observed on the Si detector is 380 mV that corresponds to approximately 2 million of detected x-ray photons with the calculated pick energy 6.5 keV. This photon number is about two orders of magnitude higher than in similar experiments at LBNL and NRL where solid state lasers have been used.

Congratulations to the participants in the run: Vitali, Karl, Shigeru, Ping. Igor, as well as to a number of people who participated in preparation of the Compton experiment! Our thanks to the EGS Section, in particular to Chi-Chang Kao and Peter Siddons for help with the detector and energy filters.

  • Conditions of the experiment:

Electron energy 60 MeV

Electron bunch charge 1 nC

Electron bunch length 10 ps

Electron focal size sigma_x=50 um, sigma_y=100 um

Laser wavelength 10.6 um

Laser energy 200 mJ

Laser pulse ~200 ps FWHM

Laser focus ~200 um FWHM

  • By inserting foil filters in front of the Si detector, the spectral content of the signal has been determined:

Ti 25 um measured T=0%. Filter characteristic: transmission below 5 keV. Only photons E>5 keV contribute to the detector signal.

Ni 12.5 um measured T=25%. Filter characteristic: transmission from T=40% at 6.5 keV to 15% at 5 keV. Conclusion: only photons with energy E in the range 5 keV<E<6.5 keV are responsible for the signal.

The observed cut off below 5 keV can be explained by the contributing factors:

a. absorption in Be window (250 um) - drops to T=0 at 2 keV

b. absorption in air - drops to T=0 at 2 keV

c. angular distribution in the Compton spectrum in combination with the limited aperture of the Si detector and drop in the x-ray brightness at lower energies.

Quantitative assessment of all this contributions requires sophisticated simulations.

  • Attempts to visualize the x-ray spot using Kodak luminescence film projected onto the cooled CCD camera with the image intensifier or directly on the CCD camera demonstrate insufficiently low sensitivity of these systems.

The main objective for the next week run are:

  • Precise measurements of the electron and laser beam sizes in the interaction region in order to make comparisons with the theory predictions on the produced x-ray photons Also any improvement in the electron and laser spot matching may lead to further enhancement of the signal.

Back to Top

VISA Experiment (Reported by Aaron Tremaine and George Rakowsky)

The test beamline (ATF beamline #3) was run this week. Work includes improving the 66MeV energy measured (attributed to low output kilowatt amp), resolution of the BPMs and multiple images of the alignment laser. Also, the probability of adding another quad to the VISA matching section is in consideration.

VISA Undulator sections have arrived from SLAC, after installation of new fiducial balls and CMM re-calibration. While at SLAC, Sections #4 and #2 were found to have developed a bow. This has been corrected. Some of the trim magnets were removed or disturbed in the process, so magnet shimming will have to be rechecked on all the sections. Section #3 and 4 are now being set up on the pulsed wire bench. Unfortunately, section 2 will have to be sent back to SLAC because of a bowing in the strongback that was found out after it was sent to BNL. This shouldn't put any more delays on the measurement schedule since sections 3& 4 can be worked on in the meantime. George and Jeff will measure the X-17 superconducting wiggler the week of Sept. 27. After that, full attention will be given to completion of the VISA undulator measurements during October.

Opticraft, the company polishing the diagnostic mirrors, said it should send out the mirrors today. Once arrived at BNL, test for surface flatness will be done. Diagnostic probes are ready, and once a mirror is inserted in one of the probes, hopefully installation of a completed diagnostic probe into the test beamline can be implemented.

Next week tests for Yag saturation will be made. If it is concluded the Yag saturates, then the VISA diagnostic pop-ins will use OTR for beam profile measurements. It appears the diagnostics can accept an OTR screen in place of a YAG for this case scenario.

The final board for the Data Acquisition computer arrived this week and software has been written. We plan to move it to its permanent resting place in the FEL diagnostics room to test out and debug all aspects of expected acquisition during the test runs.

Back to Top

STELLA Experiment (reported by Karl Kusche)

1) New wiggler design/construction continues at STI, expect to install in

beamline #1 as early as mid-October.

2) Data analysis of the last run is being carried out at STI.

Back to Top

Computer and Control System (Reported by Bob Malone)

VISA EXPERIMENT:

Software/new window displays were completed for beam line no. 3 and were exercised during the VISA test run. This includes controls for magnet power supplies, pop-in flags and video switching. All controls operated correctly with only minor errors found in a magnet power supply tabular summary. They were corrected and retested successfully.

NEW CONTROL SYSTEM:

ITD has completed all wiring needed for replacement of ATF’s CAMAC serial highway as part of the planned upgrade of our computer control system. All key locations in the ATF now have two additional runs of 100 MHz Ethernet which terminate in the control room at a fast Ethernet switch. These key locations also have new unterminated fiber optic cable stored in each junction box. Special thanks to Bill Cahill who escorted untrained contractor personnel into our controlled areas during the installation. He also coordinated the more complicated cable pulls to the C1 and C3 lab areas as well as the experiment hall.

NOTE: Users are already attempting to connect computers to these new feeds with the expectation of obtaining access to the BNL network. These cables are strictly for control and data acquisition activities internal to ATF and will NOT be connected to the external site network. This is necessary to ensure a secure, quiet environment for our control system and scientific data collection. Access to the site network has been (and will continue to be) available at every telephone junction box within ATF. Contact R. Malone (X2084) if you need help in identifying which connection to use.

Back to Top

Technical Operations (Reported by Bill Cahill)

This week we were able to complete the VISA #3a ‘test line’ including computerized operation of all magnets, pop-in’s and diagnostics. All cabling is documented and the dipole switching chassis is installed and operational. A radiation fault test was performed and no recordable levels were detected. The Compton Experiment radiation fault test was performed at 100% charge and no levels were detected. The fast detector experiment on beamline #3 is under vacuum and a radiation fault test was performed on Wed. 9/15. A radiation survey observed a peak of 12mr/hr at the external north side of the facility shielding. A scheme has been formulated by XJ Wang and Bill Cahill to modify the existing shielding to reduce/eliminate the problem. The beamline has been locked out until additional shielding is installed.

Back to Top

 

Top of Page

Last Modified: December 3, 2007
Please forward all questions about this site to: Vitaly Yakimenko