2000 ATF Newsletters

Jan | Feb | March | April | May | June | July | Aug | Nov | Dec

April 14 | April 21

 

Contents

1. Introduction

 
 

 

Hi everybody,

The HGHG experiment succeeded in implementing an autocorrelator at 5 micros and measuring the HGHG output pulse width.

The STELLA experiment worked a miracle in designing, simulating, building, measuring and delivering a wiggler for the STELLA 2nd stage in less than two weeks. Amazing! The results of the simulations look very promising for the experiment.

Ilan Ben-Zvi.

Back to Top 

STELLA Experiment (REPORTED BY KARL KUSCHE)

Two weeks ago, the decision was finalized to substitute a permanent magnet wiggler in place of  the ICA gas cell as the second (accelerating) stage for STELLA.  The quick change in direction came after many weeks of struggling with the optical alignment of the ICA's radial polarization system.  The optical alignment & characterization of the first wiggler (prebuncher) usually takes less than a day, so we expect that this second nearly-identical wiggler should be just as reasonable.  This reduction in complexity should increase the probability that positive staging results are achieved in time for AAC 2000.

At STI, calculations were done to assure proper beam and wiggler parameters;  the final design called for a 33mm period (untapered) assuming 400 MW delivered laser power

[see 4_14_IFEL_2nd_stage.htm ]. 

The fabrication and testing of the wiggler & mounting components was then finished in only 1 week!  During that time, magnetic measurements and adjustments of the new wiggler were completed to assure there was no dipole effect

[see 4_14_IFEL_final_perf.htm ].

On Friday (4/14), the wiggler arrived at ATF.  Our plan is to install/align it into beamline #1 and begin pumpout by as early as Monday evening.  Laser alignment modification is currently underway to bypass the existing ICA optics and deliver an annular vertically-polarized laser beam to the second wiggler via GPOP3 mirror.  Our goal is to be ready to run beam studies on Thursday (4/20), and look for modulation the following week.

Back to Top 

HGHG Experiment(REPORTED BY LI-HUA YU)

Wednesday we made important progress: Adnan and Marcus’s autocorrelator got a preliminary measurement for the HGHG pulse length measurement. (See report by Adnan Doyuran, below).

Another progress is the 1-D array detector begins to work yesterday after the efforts by Ron Nawrocky, Bob Malone, Timur Shaftan, and Jack Tallent. The SASE profile of single shots at 5 micron were displayed yesterday.

As reported by Adnan last week, Adnan and Marcus aligned the autocorrelator and were able to measure the YAG laser pulse length successfully, thus determined the zero position of the two arms of the autocorrelator. During the last few months, Adnan rebuild the autocorrelator to separate the two collinear beams by larger angle, so the collinear beam would be discriminated  from the non-collinear beam much more easily. We also used normalization to overcome the fluctuation.

Our main purpose was to test the autocorrelator, and due to the limited running time and the rep rate of every 20 seconds, we started to test the autocorrelator right after we obtained the HGHG signal, without trying to optimize the CO2 attenuation. So most of the time we were not working at the designed working condition. The result is that when the CO2 energy is small, such as 0.4 mJ, we may obtain large HGHG signal of order of 15 microJ in a Joule meter which took about 40% of the radiation (thus 15 microJ corresponds to 37.5 microJ in HGHG total output). And sometime when the CO2 energy is a few mJ, we get order of 5 microJ.

The output of the 2.6 micron signal is divided by the square of the 5.2 micron HGHG signal for each shot at different delay arm length, the result is plotted by Marcus in the attached figure. 

4_14_HGHG_Autocor.gif

The blue dots are for HGHG signal smaller than 15 microJ, the red dots are for those larger than 15 microJ. The horizontal axis (the delay arm position) is in unit of mm. As explained before, the fluctuation is partly due to CO2 fluctuation from shot to shot. Because the attenuation was not optimized, there are not sufficient data points for HGHG signal larger than 15 microJ. Also, near the peak (delay position 18.7 mm) the detector signal reached saturation (15 V). So the measurement still does not give sufficient accuracy, even though the apparent FWHM of these points is between 1mm and 1.5 mm (corresponds to 4 to 6 ps).

HGHG simulation and the single shot spectrum predicted the pulse length is 3.5 ps. The electron beam pulse length is about 6 ps. We need to improve our precision to distinguish between 3.5 and 6 ps. To improve the accuracy of this measurement, we need to optimize the CO2 attenuation, and improve the alignment and normalization in the autocorrelator to reduce the fluctuation of the 2.7 micron signal, and improve the statistics. This will be the topic of our next few runs.

Last night the participants are Adnan Doyuran, Marcus Babzien, Timur Shaftan, Igor Pogorelsky, and Li Hua Yu.

HGHG Autocorrelator (REPORTED BY ADNAN DOYURAN)

Last week, after successfully testing the autocorrelator with the Doubled CO2 oscillator beam, this Thursday and Friday we moved the autocorrelator to laser lab and tested  it with the YAG laser. I aligned it through the irises using CCD camera. Then I checked the beam splitter and measured the reflected and transmitted energies, there was approximately a 7 to 5 ratio, which is very good for a wavelength for which it has not been designed. Then I checked the doubled light with the photo diode, determined the crystal (BBO) orientation for both arms. I looked for the non-collinear beam, tuned the crystal angle and position to maximize the signal, and changed the delay to find the peak. Then I scanned the delay line to find the pulse length.

In the link below you'll see the signal vs. delay data. I measured Peak-to-Peak and maximum signals to get the most accurate result. They both show a pretty good agreement.

4_14_Autocor.gif

Back to Top 

VISA Experiment(REPORTED BY AARON TREMAINE)

Previous week:

Last Friday’s run We did radiation vs. charge and it is still linear:

4_14_VISA_signal.pdf

Last run caused us to think we were not seeing a clear OTR signal because only the “core” of the spot would change. A series of BPM picts with different filtering is included in the above pdf document. In the pict, much x-ray background and this caused huge error in the emittance measurements. We will need to shield the emittance measuring cameras better in the experimental hall for his measurement.

The transport is currently being installed. Once up we’ll put in the optics and align and hopefully be able to transport radiation to the FEL room, where the noise is considerably less.

We need to make sure that we are ready for the shutdown the week of May 8. This includes the new pop-in installation before Robert comes out, alignment laser stability, and interferometric laser alignment team travel plans.

This week:

Thursday and Friday were run days for VISA. We mainly studied the trajectory through the undulator. Using a simplified trajectory algorithm, the oscillation amplitude was reduced from about 3mm in the beginning to <1mm. The trajectory was improving but with 8 BPMs the process takes much time per trajectory measurement. Improvements in the data acquisition should speed up the process and reduce error. Next week we will look into the more formal algorithm and push to incorporate the orbit correction in to the controls system.

Emittance measurements made in the matching section were found to be 12 mmmrad.  There could be two problems with the high emittance measured.

The beam in our two run days had abnormal structure in the profile and the optics for the measurement are resolution limited (used YAG screen in BPM). By next run the BPM used in the emittance measurement will be changed to OTR, thus increasing the resolution and accuracy of the measurement. Emittance measurements were done on the H-line, and an emittance of 9mm-mrad was observed at 500pC. The ATF engineering report has more to say about these measurements.

Optics have been ordered (polarizers/filters) and hopefully will be here by the next run which has been changed to next Friday. It has been found the cameras pick up much spontaneous emission and filtering optics are needed to remove undulator radiation.

The shutdown for the week of May 8th is still on the agenda. The new pop-ins will be ready and installed before the shutdown week. Roberts alignment team will come out for another interferometric alignment that week.

Back to Top

VISA Laser(REPORTED BY ALEX MUROKH)

A detailed description of the VISA alignment laser:

4_14_VISA_laser.pdf 

Back to Top

YAG Laser (REPORTED BY MARCUS BABZIEN)

Monday urgent realignment of the demo oscillator was performed to restore optimum mode locking, phase stability, and output power.  Late last week all of these parameters had degraded nearly to the limit of operation.  With the experience gained on the new oscillator, Bob Harrington and I were able to achieve the same average power with much lower pump, and therefore lower heat load.  This week the oscillator performed extremely well in both phase and pointing.  No realignment into the amplifiers was required after Monday, and the system operated for experiments the rest of the week.

Today XJ and I performed some beam studies to try to understand the cause of degraded e- beam quality.  By using different masks to shape the laser profile on the cathode, we demonstrated that the e-beam imaged from the cathode through the linac shows structure in the laser beam.  Different regions of higher and lower intensity in the laser spot map onto the e-beam distribution.  This helps to explain structure observed in the e-beam after the linac.

Back to Top

Technical Operations (REPORTED BY BILL CAHILL)

Previous week:

We have finally come to the end of the road as far as the YAG laser covers are concerned. All of the units have been fabricated and installed. The remaining pop-in for VISA was installed and leak tested, everything is A-OK.  The  Smith-Purcell chamber was leak tested and is OK also. New control cables were pulled for the HGHG Experiment, allowing finer control of diagnostics. NSLS electricians have assisted with the cable pull and remedied the existing safety violations found on the last “tier 1” inspection. The “x-wing fighter canopy” cover for the terawatt laser breadboard  is in need of a structural modification. It is changing the position of the laser when operated. The unit will have to be braced from the wall, allowing complete independency from the optic table. Work will begin early next week. The Klystron cooling enclosure is developing nicely.  BNL Sheetmetal people have fabricated and installed the metal wall and will complete the hatchway and a/c unit early next week. Also on next Mondays agenda  is the modification of the Linac water circulation system plumbing.  Masons will open the shielding wall and plumbers will modify the copper lines to accept the new water system Which will be installed in May.  Thursday, we had a failure in the switching contactor for the FD5 trim.  Appears to be oxidized contacts. Repaired. The SDL had requested the return of the borrowed high voltage power supply used for the ATF gun modulator. As the new Maxwell power supply has recently arrived, this was a good opportunity to install it and field check it’s reliability. As the borrowed supply was being disconnected, it was found that an ac lead for the incoming power had become loose. This would have been difficult to find if it weren’t for the supply change. After the reinstallation, the stability greatly improved. This might have been the major cause of the mysterious jitter.  Time will tell. Marc Montemagno has fallen victim  to his legal obligations and is on jury duty. It is expected to last all of next week. We will feed the accelerator gods handsomely in order to avoid disaster.

This week:

The electronic support for the ATF was interrupted this week due to jury duty. Marc will be back on Monday. Monday’s Maintenance Day was very productive as it allowed us to utilize the services of the BNL Masons and Plumbers to remove the Linac shielding and modify the water lines to accept the new, still under construction, closed loop water temperature control system. This new array should be ready for installation in the upcoming shutdown. The Klystron area hatch enclosure and new air conditioning unit have been installed and we are awaiting the electrical service installation.  The unit should be operational by Tuesday morning. The defunct personnel a/c unit for the Control Room is being replaced. Just in time for the upcoming warmer weather. Aside from the normal operational support, we spent most of the week cleaning up the facility and tending to the needs of various support  groups. The Terawatt breadboard optic enclosure has been modified to alleviate the vibration and is now a stand alone unit. Don Davis has been working steadily to improve the covers and  mechanics of the system and along with John Skaritka,  will see it to completion. The VISA beam transport covers have been installed by the NSLS Mechanical Group and should bring that phase of construction to a close.

Back to Top 

Friday Engineering Meeting(REPORTED BY XIJIE WANG)

Previous week:

1.                  Next Monday maintenance: three major jobs planned:

A.    Preparation for linac water system improvement (Cahill and Harrington)

B.    YAG laser oscillator alignment (Marcus)

C.    Network connections, this may interrupt the e-mail.

2.                  this week operation:

A.    CO2 alignment problem prevented HGHG experiment from taking data.

B.    Fix Magnets power supply and relay circuit problem.

C.    Install new charging power supply for the gun modulator, return SDL power supply.

3.                  YAG work: improvement of the YAG laser profile on the cathode will be the major focus. We also discussed how to improve the humility in the YAG room.

4.                  TW CO2 laser work: Igor reported that the final decision on the discharge cell  repair should be made next week. Major work will be fixing the cover.

5.                  Fast detector experiment will exchange next Friday running time with VISA for May 23 run.

6.                  UCLA requested decrease the magnetic bunch compressor ID to 13.5 mm from 15 mm.

 

This week:

 

1.                  ATF schedule modification: To help HGHG and other ATF experiments, I have discussed with parties involved to modify next week ATF schedule by exchange experiment dates: Monday: ATF maintenance, Tuesday -Wednesday: HGHG, Thursday: Stellar, Friday: VISA. To compensate the lost date, HGHG will give up two days in the May. May 2 to Stellar, and May 24 to fast detector experiment.

2.                  Next Monday ATF maintenance jobs:

a.     Checking RF gun field balance due to the temperature variation (XJ and Harrington).

b.     YAG laser improvement: to improve the YAG laser profile and spatial stability (Marcus).

c.      Install new IFEL undulator (Karl and Done).

3.                  Next shutdown jobs: It seems YAG oscillator will not be ready for the shutdown (week of May 8), we hope to install the chiller for the amplifier. ATF will focus on getting the new linac water system ready for the shutdown, Mark will focus on the electronics, and Harrington will work on the plumbing.

4.                  TW CO discharge cell still waiting for the decision, optics cover was fixed this week.

5.                  ATF operation:

A.    QE of cathode dropped by about a factor of two on Thursday, and we have established a correlation between the HGHG runs and all last four QE drops. The best guess is that, CO2 laser or 5 micron HGHG radiation causes the release of some elements that contaminate the cathode. More detailed studies are needed, but a more powerful ion pump installed at HGHG will definitely do no harm.

B.    Linac and gun water temperature drift: I have observed both linac and gun drift about 0.5 deg C on Friday. Linac water system improvement is under construction while gun solenoid water system is on order.

C.    Gun and linac RF system: We have observed both linac and gun RF systems instability between 5 and 7 PM.  I will ask Mark to check connections and install some monitors.

D.    Emittance studies: we have tried to measure the emittance at 71 MeV for VISA. We observed many structures in the e-beam, using an imaging technique we were able to trace the major source to the laser profile, and maybe some from non-uniformity of QE due to QE drop. At such high energy, the emittance measurement is much more sensitive to the measurement error and resolution of the BPM. We have measured a large emittance 8 - 10 mm-mrad (normalized rms) for 0.6 nC at 71 MeV, and 6 mm-mrad at 54 MeV for the same gun condition (just adjusted solenoid magnet). More studies are needed to understand this. Two possible explanations are: First - measurements are dominated by the measurement error, another - emittance compensation is better matched at lower energy due to strong edge focusing from the linac entrance. We intend to continue this study next week after laser improvements.

7.                  Next Monday (April 17) 9:30 AM ATF BLOSA training at the ATF conference room. Starting Tuesday, April 18, all ATF users are required to have BLOSA form before starting work at the ATF.

Back to Top 

ISM Feedback and Improvement Corner (ILAN BEN-ZVI)

 

In the Friday ATF meeting, we discussed the material below:

Lessons-learned - NSLS Requirements for Configuration Control of Radiation Security and Shielding Systems, Bob Casey, NSLS Associate Chair for ESH/Q.

Recently an active beamline radiation interlock system for X17B2 was disconnected when components for the beam line were being removed.  The beam line itself had not been used for some time, and it was understandable why an impression had developed that the security system was inactive.   One of the lessons-learned from the incident was to ensure that all staff were advised of the issue and reminded of the NSLS Configuration control practices for interlock systems. 

----------

Radiation Safety at NSLS beam lines depends on shielding and interlock systems. A configuration control program is in force to ensure that these are in place and functioning to provide protection. This means that before any shielding or safety system may be moved or modified, there must be a review and authorization for the activity. To accomplish this, we have two NSLS Safety System Work Permit forms which are available in the Control Room, one for work affecting beamlines and another for work which affects the injector or storage rings. The ATF and SDL have similar forms to be used for work in those facilities.

Everyone who does work on the experimental floors or in the machine areas is responsible for knowing and obeying the restrictions on work affecting shielding or safety interlock systems.  Anyone who initiates work which impacts a radiation security system or removes shielding must obtain and post a Safety System Work Permit at the work site and ensure that any required safeguards have been put in place before starting the work.   Anyone who joins a job in progress which involves moving shielding, modifying beamlines, or working on safety systems must verify the status of the permit or other authorization for the work.  If there is any question, usually an Operations Coordinator can provide an answer or determine whom to ask.  The operations groups at the ATF and SDL will know the status of permits for safety system work at those facilities.

Most of our shielding is pretty obvious: concrete, lead bricks, and hutch walls.  Other structures may provide shielding as well: beam pipes and other components such as monochromator tanks.  There are parts of the interlock systems which may not be obvious, for example, the overhead lights in hutches and tunnels are connected to the interlock as part of the warning system.  Because of the nature of the interlock systems, the interlocks associated with beamlines and hutches which are not in service are usually still connected to the rest of the safety system.  All of these things are under configuration control, and a permit must be approved before work is done on them.  If you are ever in doubt regarding this issue, get the necessary information before beginning the work.

Consult NSLS SEAPPM NS 3.4.1b for detailed procedures for using Safety System Work Permits.

Back to Top

 

Top of Page

Last Modified: December 3, 2007
Please forward all questions about this site to: Vitaly Yakimenko