![]() |
![]() |
|
Site Details ATF Newsletters |
2000 ATF NewslettersJan | Feb | March | April | May | June | July | Aug | Nov | Dec
1)
Beamline #1 nearing state of readiness for the next group of runs,
as detailed in previous report. 2) Modeling
at STI - Loren Steinhauer and Wayne were able to simulate space charge
effects through the beamline (after exiting the wiggler); the model’s
results appear to predict Jan 7 results (energy spread 1-1.5% using 42MW
delivered) to the correct order of magnitude.
We are planning to use the model to understand space charge limitations
to basic experimental parameters (i.e. maximum e-beam charge to be used,
etc.), Wayne expects the final result to define a limitation in the amount
of charge we can use. 3) VOx
imaging system has been completed for the ICA gas cell, which will be
shipped back to ATF for installation during the next shutdown. 4) Wayne
& Christian plan to come to the ATF during the last week of February
to assist the local team during the several days of running to recommission
the ICA system.
We ran this last Tuesday. What we saw during the run: A Molectron detector was set up at the FEL mirror of Pop-in
8. When the flipper was down
(no radiation from inside the undulator to the detector) we saw 50mV of
background. When up (radiation from
undulator gets to detector), we saw 400mV or about 1.7nJ (from the manufacturer’s
calibration). This radiation
was linear with charge. Calculations show the expected amount of spontaneous
emission expected for our angular and frequency bandwidth to the detector
is about ~1.5nC. It appears that the measured energy is within error to
the expected spontaneous. BPMs: Our main mission here is to engineer BPMs with OTR. We can
see plain OTR with sensitive Cohus and the Hitachi can give a reasonable
signal. Also, the Hitachi does
give an image at 4 (OTR+ BPM optics), but this signal is weaker than all
the rest. It looks like the way to go is to use OTR/BPM with more sensitive
cameras, but more testing is to be done.
One note: We must be cautious not to confuse spontaneous emission
with OTR through the BPMs (cameras) which would be very sensitive to the
energies above. Magnets: As discussed before, there is very little room between the
steering magnet pole piece and the BPM optics. Removal of this pole piece
leaves us with a C-magnet. The
measured higher order effects from lack of symmetry gives a quadrupole
field much less than a percent of the undulator field. It looks as though
the near term solution is to run with a C-type steering magnet, but other
solutions are being looked into. It may be down the line that 450 windings
would not give the resolution needed, and may have to return to a lower
winding. If it only takes
~150 windings to give the necessary steering, the steering magnet and
BPM optics could co-exist. We are going to try this on one of the steering
magnets. (We do have extra pole pieces).
Pulse shortening by saturable absorber: Testing of the saturable
absorber shows good results so far. The first sample was received in September
and measurements on the bleaching at high intensities were made.
The material is LiF which is exposed to radiation to cause lattice
dislocations that act as color centers.
The color centers have broad absorption around 1 micron and relatively
high cross section. The amount of pulse shortening depends upon how much energy
is used for bleaching, but simulation shows using 1/3 the total pulse
energy shortens the IR from 14 to 10ps FWHM, with the leading edge of
the pulse experiencing all the shortening.
The first test of the simulation was to use a short section of
saturable absorber, only 25 out of 75 mm and measuring the changing transmission
versus intensity. The only
parameter required for comparison with the simulation is the unsaturated
absorption, which depends upon the amount of radiation absorbed and hence
the concentration of color centers and the length of crystal.
The measured and simulated data are shown in the figure 1_21_Sat_absorber
Except for low energies, where the measurement was dominated by noise,
the agreement is very good. The
measurement was performed with two pulses to determine if the recovery
time is sufficient to shorten both of the pulses generated in the YAG
system. The spacing between
the CO2 slicing pulse and the gun pulse is 245 ns, and complete recovery
was observed in this interval. More
pieces are on order to provide the anticipated shortening, after which
streak camera and electron beam measurements will be used to confirm the
results. Joulemeter: A more sensitive joulemeter probe was installed
in the gun hutch to improve the signal to noise ratio at the low energies
now delivered to the cathode. The
background noise with no laser power is now about 1% for the few microjoule
energies now encountered and depends strongly upon gain settings in the
digitizer used. We can now
accurately measure laser fluctuations in the gun hutch, as they are now
considerably larger than the joulemeter noise. Cathode monument: A new lens system was installed in the
gun hutch to collect more light from the cathode monument.
There is now enough image brightness to measure the beam profile
at a few microjoules delivered energy. New oscillator: Finally, the new oscillator from Time Bandwidth
Products arrived before the end of the year.
Brief measurements so far indicate over twice the power output
of the current demo unit we are using.
A few measurements of the power stability over two days indicate
better than 2% p-p. Pulse
duration, phase, and pointing stability measurements will follow. We have completed the cable labeling and assignments for
the installed VISA wiring. These cables are now official and are entered
in the cable log database. A major breakthrough in the Eurocrate power
supply mystery. Marc and Aaron have been investigating the problem and
it occurred that the voltage was the common denominator for all of the
errors. Upon lowering the input voltage in steps, it was observed that
the reason the units were behaving poorly was the supply voltage was too
high. The design, we feel, called for 5vdc, we were operating at 10vdc.
Upon reducing the supply voltage to 5vdc, the problem seems to be solved,
although we still have occasional drift at the high end. We feel the drift
is being caused be a thermal effect as we increase the current past 2.75
amps.. The fan pack cannot remove the heat fast enough and causes instability
in the electronics. This was proved with “cool-spray”. We feel the system
will not need this high current so all things being equal, it should work
fine. We would prefer to operate at 10vdc in order to reduce line loss,
the investigation continues!
Last Modified: December 3, 2007 |
||||||||||||