2000 ATF Newsletters

Jan | Feb | March | April | May | June | July | Aug | Nov | Dec

March 10 | March 24 | March 31

 

Contents

1. Introduction

3. VISA
 

 

Greeting everybody,

The ATF entered an unscheduled shut down this week when a modulator high-voltage power supply AND a Pockels cell power supply failed. Emergency repairs are in progress.

Before the shutdown we had runs of STELLA, the Ultra-fast Optical Detector and longitudinal tomography. In addition we have the usual collection of progress reports from various experiments and the facility.

Ilan Ben-Zvi.

Back to Top 

STELLA Experiment (REPORTED BY KARL KUSCHE)

During the period of 2/28-3/3, the STELLA Experiment had two days planned for laser alignment and three days for electron beam tuning and interaction studies.  Murphy’s Law seemed to be in effect, however.  The complex laser alignment of the ICA system required more time than anticipated.  Then, the first check of the e-beam transmission through the ICA gas cell revealed the need for adjustment of the cell’s alignment with respect to the last quadrupole triplet.  The first test of the new VOx target system with the ATF’s GW CO2 laser revealed problems that forced a redesign.  Finally, by the last day of the run, equipment problems with the linac brought any further e-beam interaction studies to an end.

Nonetheless, the ATF-STI team made important progress:  the laser alignment is nearly finalized, the gas cell and the rest of the beamline are aligned, and the VOx target has been replaced with a fiber cross BPM.  During this past week, other improvements to the laser alignment process, fiber cross BPM, and STELLA delay line have been made.  Next week’s runs (only two days) will include further e-beam studies using the Smith-Purcell BPM’s to improve the STELLA tune, testing the new fiber BPM, and achieving rough synchronization of both beams at the ICA cell.

Back to Top   

VISA Experiment (REPORTED BY AARON TREMAINE)

We slowly pumped down the system and the vacuum looks good. We are going to turn on the ion pumps on Friday and should have vacuum ready by our next run day, March 17.

The BPMs and detectors need to be setup and will be done by the end of the weekend and will be ready by our next run.

After pumpdown, it was found that 5 out of the 7 pop-ins are now making contact with the undulator. We pumped on the system as slowly as we could to prevent movement which apparently didn’t work (none were touching before pumpdown). A smaller design (in the vertical dimension) is needed and being worked on for implementation during the next  shutdown.  The alignment lasers (800nm &566nm) were aligned as best as could be done.  There is much instability in this system (vibrations, thermal drift, air currents, mirror pointing resolution) and the alignment lasers are only to within 100um of the magnetic axis. We are currently evaluating what needs to be done in order to attain the alignment lasers to be within 20um of the magnetic axis. As long as the stability is good enough, guiding the e-beam to the alignment laser is possible, but will take more time than if it was within the 20ums.

The more sensitive cameras have arrived and we are working on a plan to implement them into the BPM system. These COHUs are bigger than the original Hitachis and there is not much room on the table so minor modifications will be needed.

The red-heading was been done for the transport. We are waiting for the materials to enclose the transport to arrive. Once here, hopefully by the end of next week, we will finish the transport for the radiation out the end of the undulator  to the FEL diagnostics room.

Back to Top 

Ultra -Fast Optical Detector (REPORTED BY JANNIS SEMERTZIDIS)

 

Recent runs, dedicated to the detection of the ATF beam bunches through the electro-optical effect with poled quartz optical fibers, were unsuccessful.  Although the best fibers we’ve produced have electro-optical coefficients measured to be two orders of magnitude smaller than LiNO3 crystals, they were calculated to be adequate for characterization of the ATF beam. Their primary virtue is that they are quite inexpensive compared to LiNO3 crystals.

We have redesigned and installed our detector package which now contains the optical elements other than the laser and photodiode detector in the beam line vacuum and to couple the output light to the photodiode through a multimode rather than a single mode polarization maintaining fiber.

Our  March 8 run was devoted to further studies of electro-optical crystals, including rise time determinations with faster oscilloscopes and with the goal of eventually employing a streak camera with visible light. We were able to reproduce earlier results by observing both the polarization dependent electro-optical signal with the ATF beam approximately 5 mm from a LiNbO3 crystal and the polarization independent attenuation of the laser light with the beam incident on the crystal. Although some useful data was obtained the run ended early with the failure of the ATF modulator power supply. 

A paper describing our previous results with LiNO3 was submitted to Nuclear Instruments and Methods in Physics Research A.

Back to Top 

Longitudinal Tomography (REPORTED BY SHIGERU KASHIWAGI)

We tried the longitudinal tomography beam study on March 7th 2000 and we had planned to measure the longitudinal phase space distribution with various laser energies (=various charges) and same rf-gun phase.  By changing the power of YAG laser, we will be able to observe a longitudinal phase space effect in the rf-gun.

The setup at the ATF, following the pioneering work at Stanford [Crosson, E.  R., et al, “A Technique for Measuring an Electron Beam’s Longitudinal Phase Space with Sub-picosecond Resolution,” in Micro Bunches Workshop, AIP Conference Proceedings 367, 397-405 (1996)], is shown below:

http://nslsweb.nsls.bnl.gov/AccTes/R0/3_10_long_tomo_setup.htm

The longitudinal phase space reconstructed image, the first measurement of its kind for a photoinjector,  is shown below:

3_10_long_tomo_image.jpg

In the last beam study, at some point the connection between the personal computer (Mathcad) and main database system of ATF froze. I didn’t take data. Bob guessed a problem in the taking of a image using grabber system.  In my Mathcad program, I didn’t stop the grabber system at the time of saving the image. (I used the grabber system in continuous mode.) So I modified the Mathcad program using single shot mode of the grabber system. I need to check this program.

At the next beam test, we will try to observe the longitudinal space charge effect in rf-gun by changing current at constant gun phase.

Back to Top 

Computer Control System (REPORTED BY BOB MALONE)

 

HGHG Experiment / Facility:

Software to read the new diode array diagnostic has been completed and tested as far as possible without real signals.  This system uses our standard KSC 3516 scanning ADC but strapped for external triggering.  Users must supply a TTL pulse to initiate analog to digital conversion of the unit’s 32 channels.  Software will collect and display these values on each ATF rep rate clock pulse.  Next week, with M. Babzien and R. Nawrocky, we should be able to incorporate the sample and hold hardware for final testing of the system.

Back to Top 

Beam Weekly Measurement (REPORTED BY VITALY YAKIMENKO)

A Mathcad program was developed to measure various e-beam parameters for the Weekly report. The program will be expanded as conditions permit. The output (in PDF format) is at:

Beam_pars_3_10.PDF

The file provides the charge vs. phase scan, charge vs. laser energy, quantum efficiency, maximum charge, charge at operating phase,  etc.

Back to Top 

Technical Operations (REPORTED BY BILL CAHILL)

Report from previous week: The new circuit breaker panel for additional power was installed by NSLS Electricians and is now ready for service. Most of the week was spent fabricating the new linac temperature control station which will be located below the linac klystron. This will be an ongoing task as parts that have been ordered will be installed until the system is complete. Assistance was given to the HGHG Experimental Group involving small machining and other various tasks. Bob Harrington has assembled a test dock in order to evaluate a scheme for regulating the temperature for the RF gun. The set-up is located in the YAG lab and is undergoing analysis.

This week started out upbeat and went downhill quickly. The initial problem started with the Linac stability. It didn’t take long before we realized that the linac modulator high voltage power supply was failing and as predicted, according to Murphy’s law , died. As the newly ordered Maxwell power supplies have not yet arrived, a quick fix was to borrow the spare Spellman power supply from NSLS. This too had failed upon installation. The next resort was to install the last remaining spare from NSLS, alas, this was also a dud. Being dead in the water, the ATF’s original power supply was hand carried to Spellman Electronics in Hauppauge for emergency repair. We should know the diagnosis by Monday. As this was not enough of a setback for operations, we were informed of a situation involving the YAG laser system whereas the Pockel cell high voltage power supply failed. After investigation, we found the bad high voltage board and contacted California for emergency repair. The unit was also hand carried for immediate shipment and hopefully will be back by early next week. In the meantime, we are installing an additional water controlled temperature stabilizer coil for the rf gun. Assistance was given to the CPOD Experiment and several ion pump holding power supplies for HGHG were built for easier pumpdown. The monitor stand for HGHG diagnostics is being installed in the Experiment Hall and we still had a little time left over for clean-up. All in all, a busy week!

Back to Top 

Friday Engineering Meeting Summary (REPORTED BY XIJIE WANG)

Following topics were discussed at this afternoon engineering meeting:

1.   Don Davis will start work at the ATF next Monday on the CO2 laser under Igor Pogorelsky. Bill Cahill will be response for tracking his job assignments. If VISA needs him, Igor must be consulted.

2.   Modulator power supply: we are pushing on two fronts, one is get new one delivered, and other one is to fix the old one.

3.   Yag laser Pockel cell power supply: we have shipped the whole unit to the manufacturer by express mail. Marcus will work with Bob Harrington to improve the YAG laser table optical layout.

4.   We are installing a new cooling system for the gun. It will be tested next week.

5.   TW CO2 laser system: John and Igor reported that, a plan for fix the TW laser cell is in place. Igor will prepare a detail plan for CO2 laser operating at 30 ps (FWHM) and 10 J energy.

6.   Schedule: Please submit your running time request for April, May and first half of the June. We also plan to have a one week shutdown in the late April or early May to install new laser system if everything works out.

Back to Top 

Top of Page

Last Modified: December 3, 2007
Please forward all questions about this site to: Vitaly Yakimenko