2000 ATF Newsletters

Jan | Feb | March | April | May | June | July | Aug | Nov | Dec

May 5 | May 19

 

Contents

1. Introduction

2. STELLA
 
  

Greetings,

The new exciting developments: Staging experiments have started in STELLA and gain observed in VISA.

Ilan Ben-Zvi.

Back to Top

STELLA Experiment (REPORTED BY WAYNE KIMURA AND KARL KUSCHE)

The STELLA experiment ran for 3 days this past week and accomplished a number of important objectives.  We successfully commissioned the new second permanent-magnet IFEL, which was installed last week to replace the ICA gas cell as the accelerator stage for the experiment.  We also reestablished modulation in the first IFEL (i.e., prebuncher), which is located upstream from the second IFEL.

The first figure shows a typical e-beam energy spectrum with no laser beams driving the IFELs.  (Energy dispersion is on the abscissa.) The intrinsic energy spread is approximately 0.1% (1-sigma) with the mean energy set to 45.6 MeV corresponding to the resonance energy needed for the first wiggler.

5_5_STELLA_Laser_off

The second figure shows the energy spectrum from the first IFEL (i.e., prebuncher) with no laser driving the second IFEL.  The double peaks predicted by theory can be clearly seen in the picture and are centered symmetrically about the mean energy (c.f., laser-off figure).

5_5_STELLA_IFEL1_only

The third figure shows the energy spectrum from the second IFEL (i.e., accelerator) with no laser driving the first IFEL.  In this situation the second IFEL behaves like a modulator.  However, because the second wiggler is designed for a slightly higher resonance energy (46.3 MeV), the model predicts the modulation spectrum should be slightly offset from the mean energy point in the positive direction.  Indeed, comparing the first and third figures we see there is a positive offset.

5_5_STELLA_IFEL2_only

Next, the two IFELs were operated together.  This is the first time two IFELs have been staged together.  (During our last run in March, we demonstrated for the first time staging together of an IFEL and ICA system.) The resultant energy spectrum was measured as a function of the phase delay between the laser beam driving the first IFEL and the laser beam driving the second IFEL.  (This is the first time we tried using the fine stepper motor on the trombone delay line, which is capable of 0.4 microns/step.)

Copious amount of data were collected during the run.  The CO2 laser was shot over 400 times.  Over 140 energy spectra were collected.  We probably set a new record for the STELLA experiment on the amount of data obtained during one day.

The model predicts that the energy spectrum should contain specific features, which change in shape and position in energy depending on the phase delay between the two IFELs.  The energy spectra when running both IFELs certainly did change in shape, but not in a manner predicted by the model.  We will be analyzing the data and exercising the model during the next weeks to better understand what occurred during the experiment.

Several factors could be causing this disagreement.  First, the model is an idealized one and does not include 2-D effects.  This latter point may be important because during the experiment, the e-beam transverse dimensions were comparable to the laser beam focus size inside the wigglers and were not always symmetric in shape (i.e., the e-beam transverse profile was highly elliptical at certain locations).  The amount of effective laser power being delivered to the second IFEL may be less than needed to clearly see the trapping of the microbunch [e.g., the modulation seen for the second wiggler (i.e., the third figure) is about a factor of 2 less than expected.] There are indirect clues that we may be still undermodulating the first IFEL, which might mean poor microbunching is occurring at the second wiggler. 

The next major STELLA run is scheduled for May 16-19, 2000.  Some hardware changes will be made to improve our ability to better focus and coalign the e-beam and laser beams inside the wigglers.  Vitaly will also have a 1-day run on May 2 to improve his tune of the e-beam through the wigglers in order to have more symmetric and smaller e-beam profiles through the wigglers.  Work will continue on the IFEL/IFEL model to help us better simulate the actual experimental conditions.

Following the run:

1)   New wiggler on beamline #1 was realigned via HeNe, pop-in cameras calibrated for proper ND filter attenuation for centroid determination, and beam studies followed to improve tune.  The beam profile downstream of the new wiggler was originally though to be distorted due to a problem with the wiggler itself, but a short run today proved otherwise and obviated the need for shimming and/or magnetic measurements.  In fact, the spot size and position held to within a fraction of the beam diameter when the wiggler was lifted out of the beampath.

2)   At STI, preliminary simulation results suggest that the e-beam focus size, energy spread, and emittance (beamline #1 tune) may have been too large during last week’s runs for optimum bunching, thereby making it difficult for staging effects to be observed.  Further investigation is needed, and group discussions will be held next week.

Back to Top

VISA Experiment (REPORTED BY AARON TREMAINE)

Friday 4/21/00 we ran from 9am to 2am.

XJ started at 9 am with laser profile and e-beam profile studies in the tunnel because there was observed structure in the e-beam profile.  When we ran beam through the undulator (2pm), we studied the e-beam trajectory relative to the alignment laser. Since the horizontal was studied last time we focused on the vertical trajectory through the undulator. As expected it was much easier to contain. At first the peak-peak was ~1mm.  After about an hour of upstream steering magnet changes, the peak-peak was found to be <200um. This correction is repeatable and  we made this trajectory correction twice during the run.

Detector vs. Faraday cup measurements were made.  Better collection of radiation could possibly help.  Since the detector is inside the experiment hall, x-ray background noise adds error to the lower charge measurements More information, including graphics, can be seen in the following pdf file:

4_24_visa status

Thursday April 27 was a VISA run day. XJ  started tuning the beam at 9am, and we sent beam through the undulator at noon. The most stable time for the system is after 6pm. XJ, Alex and I called it an early evening and shut down at 10:30pm.

The beam was run @ 70.9MeV with an energy spread of <.3% full width.  We were able to correct the vertical trajectory to within 100um of the alignment laser. The best we could do with the horizontal was peak-peak of about 1.8mm.

Detector vs. faraday cup measurements were made, and the plot appears to be non-linear- an indication of gain.

A shutdown will occur the week of May 8 in which another interferometer alignment will be done. I will send out a schedule for the next two weeks.

More information, including graphics, can be seen in the following pdf file:

4_28_visa status

Back to Top 

Technical Operations (REPORTED BY BILL CAHILL)

Monday’s Maintenance Day proved interesting in the never ending rf jitter scenario. Most of the complaints concerning beam jitter were geared mainly to the linac. Marc spent the entire day troubleshooting the low level system in both modulator controllers and found several “sma “ connectors loose in the gun section. After a complete shakedown, the jitter problem has basically disappeared. It  looks as if the problem was actually in the gun area and somehow masked itself. We learn something every day. A problem was resolved with the YAG Pockels cell high voltage cable and a defective low level power supply is suspected in regard to a mirror motor on the HGHG line. The experiment is working around it until we can afford the time to repair it. Bob Harrington has been trying to fabricate and complete the water system for the YAG amplifier and pre-amplifier due for installation in next week’s shutdown. We have come to a complete standstill due to the lack of parts and the lack of cooperation from the central stock system. As the stockrooms only open on half days, the delivery schedule has shifted from ˝ day to 3 days. Due to the lack and elimination of the mass majority of parts, everything has to be outsourced, taking up valuable time for ordering. This is presenting a big problem.  Beamline #3 has been bled up for VISA and “Fast detector” work, a clean-up of our machine tools in 820A was  needed at the request of DAT and as always, aside from mandatory training, provide support for  ATF operations.        

Back to Top

Friday Engineering Meeting (REPORTED BY XIJIE WANG)

Friday 4/28/2000:

1.   ATF schedule: next Tuesday HGHG run will for STELLA, and Friday beam studies requires ATF experimental hall interlock.

2.   May 8th ATF shutdown: due to delay of the parts, both oscillator and linac water will not be ready for the shutdown. Two other jobs will be scheduled. One is the laser amplifier water system (Harrington), other is to test both low level and 1 KW RF system (Mark). Beam testing is scheduled for Thursday (May 11) and Friday (Yakimenko)

3.   YAG laser work: Mark should fix the Pockels cell cable first thing Monday, and check the heater power supply for the amplifier.

4.   CO2 work: Mark will make grounding cable for the new CO2 charging power supply. Don will work for VISA from May 4 to May 15 (inclusive), once discharge cell is back to ATF, both Don and Harrington will work on the CO2 after shutdown.

5.   VISA request exclusive access from Friday May 12 8:00 AM to Monday (May15) 12:00 PM.

6.   Both VISA (including matching section and beam pipe after the undulator) and fast detector request vacuum bleed up on Thursday (May4, Harrington).

 

Friday 5/5/2000:

1.   ATF facility safety and operation procedure: several incidents took place this week that require immediate action. One is that  the ATF experimental log book disappeared from control room until this afternoon, the other is that the check list and operations log were not filled,  and control room door left open overnight.  All ATF operator and duty operator will be re-trained next Friday 1:15 PM, and no ATF beam operation will take place until that time.

2.   Next week ATF shutdown: Mark will check all RF connections, tune up both 1 kW amplifiers, and install new capacitors, Harrington will help on the linac water system, and TW CO2 cell hydro-testing.

3.   Fast detector requested to install a new stand, Harrington will check to see how safety looks.

4.   Harrington suggests make sure yellow tag will attached to the vacuum valve if one side is on the air, I agreed.

5.   VISA: Don will work for VISA next week full time, VISA exclusive access start Friday, and end next Monday. STELLA laser alignment need to work in the experimental hall next weekend, I think they should be able to accommodate each other. I asked Marcus and Alex to put up signs for SLAC alignment laser this afternoon.

Back to Top  

ISM Feedback and Improvement Corner (ILAN BEN-ZVI)

 

Thanks to Xijie Wang and Eva Rothman, the ATF users training has been standardized as BLOSA training. A form has been placed on the web at:

http://nslsweb.nsls.bnl.gov/Training/ATF/atf-blosa-form.doc

All current ATF users have been retrained by Xijie under the new format, and the list of trained users, maintained by Eva, is also on the web at:

http://nslsweb.nsls.bnl.gov/Training/ATF/atf-blosa.htm

Xijie Wang, Bill Cahill and Marcus Babzien are the qualified ATF BLOSA trainers.

 

Back to Top

Top of Page

Last Modified: December 3, 2007
Please forward all questions about this site to: Vitaly Yakimenko