Computer and Control System
|
| |
February
23, 2005: In mid-June 2004, failure of a primary cooling
fan caused a power supply to overheat in our venerable VAX-based
computer control system which had been in service for 14 years. |
| |
April-May
2003: The ATF web site has been redesigned. |
| |
October-December
2002: Upgrade of the ATF control system continues to make
substantial progress and will soon be completed. |
| |
March
2001: As reported in an earlier ATF Newsletter, the new
control system computer has arrived. |
June/July
2001: Since the beginning of June, there have been two major
accomplishments in the ATF computer control system upgrade, Successful
porting of user display windows and concurrent hardware sharing.
|
September
2001: The long awaited 100 MHz Ethernet CAMAC crate controllers
have arrived, replacing the 10 MHz units which were on loan from
the manufacturer pending final delivery of the 100 MHz components. |
| |
January
14, 2000: Control displays and software were ready for the
first VISA runs on Tuesday and Wednesday. |
March
10, 2000: Software to read the new diode array diagnostic
has been completed and tested as far as possible without real signals. |
August
25, 2000: Planned upgrades of ATFSERVER1 are now completed,
as follows..... |
| |
March
19, 1999: Software/operator interfaces for new 30A power
supplies completed and tested. |
March
26, 1999: Orders have been placed for components needed
to build a duplicate frame grabber system and to improve the performance
of the existing one. |
May
14, 1999: Cathode cleaning performed twice: May 8 and May
13. Laser energy fluctuations noted as function of position on cathode.
|
May
21, 1999: Testing of new emittance measuring program completed. |
May
28, 1999: Program for YAG energy feedback has been written.
Debugging in progress. |
June
4, 1999: Debugging continued on the YAG slow drift energy
correction software. |
July
9, 1999: As part of the network upgrade for building 820,
both the 10MHz thick wire network backbone (yellow coax) and the
thin wire (black RG58) will be disabled and/or removed in about
30 days. |
July
16, 1999: G. Rakowsky provided us with information on how
to drive the correcting coils associated with the dispersion magnet.
|
July
23, 1999: Emergency replacement for the control system’s
ailing disk drive was completed Monday morning as planned. |
August
6, 1999: New ATF control system development effort..... |
August
27, 1999: Software changes, needed to accommodate beam line
3 magnet reassignments, are underway. |
September
17, 1999: ITD has completed all wiring needed for replacement
of ATF’s CAMAC serial highway as part of the planned upgrade
of our computer control system. |
October
1, 1999: As part of ATF’s control system upgrade,
we have been extensively testing Vista’s Vsystem software
tools operating under Linux on Intel PC hardware. |
October
22, 1999: Tests/learning of new Vsystem software under Linux
continues. |
November
19, 1999: Intensive testing of the new Vista software under
Linux continues. In particular, a key problem with software interrupts
and inter-process communication via reliable signals has been resolved.
|
December
3, 1999: IMPORTANT NOTICE TO ALL ATF CONTROL SYSTEM USERS
Due to the recent attempts by hackers to break into BNL computers,
the main ATF control system no longer accepts incoming requests
from non-BNL machines for many services including telnet and ftp. |
December
17, 1999: A block of temporary IP addresses has been set
aside for dynamic allocation (DHCP) by ATF users. |
|
|
May
2001: ATF supported six experiments in the last five months.
These are .... |
August
2001: ATF had very successful operations in August despite
the shortage of manpower and the heat wave. |
October
2001: ATF was shut down for the week of October 22 for scheduled
maintenance. During the shutdown we did miscellaneous facility maintenance
jobs, new computer control system tests and installation of three
new experiments. |
|
January
14, 2000: During these first few weeks of the New Year,
a large effort was placed on the VISA experiment. |
January
21, 2000: We have completed the cable labeling and assignments
for the installed VISA wiring. |
January
28, 2000: Aside from the snow and ice, and the temperature
dropping to 55 degrees inside the facility, business at the ATF
was normal. |
February
4, 2000: Marc Montemagno has been completing the ordering
phase of the new linac water temperature control system. |
February
18, 2000:During these past two weeks of maintenance, we
were able to complete many tasks. The aging condenser coil for the
experiment hall air conditioner was replaced by plant engineering
a/c group. |
February
25, 2000: During this short week and back to running, we
experienced a failure on the high energy slit. |
March
10, 2000: The new circuit breaker panel for additional power
was installed by NSLS Electricians and is now ready for service. |
March
24, 2000: The week was filled with frustrations on three
fronts. The initial failure with the high voltage Spellman power
supplies associated with the ATF linac led to the continuing search
for the new Maxwell replacements. |
March
31, 2000: This week started with the replacement of the
bent pop-in on beamline # 3. |
April
14, 2000: We have finally come to the end of the road as
far as the YAG laser covers are concerned. |
April
21, 2000: Monday Maintenance Day involved the opening of
the gun clamshell and tuning for field balance with the network
analyzer borrowed from the good folks at the 200 MeV Linac. |
May
5, 2000: Monday’s Maintenance Day proved interesting
in the never ending rf jitter scenario. |
May
19, 2000: Coming out of the maintenance period and into
operations went pretty smoothly. The cable assembly that operates
the transport plug door was replaced by Bob Harrington and works
better than ever. |
June
9, 2000:The terawatt laser vessel has successfully passed
all inspection criteria’s and has been reinstalled at the
ATF. |
July
26, 2000: Over the past two weeks we have been able to move
our people into the new offices of 820-M. We now have all of the
ATF staff under one roof. |
August
25, 2000: With the arrival of Igor Pavlichin, the Terawatt
laser re-assembly is in full swing. |
|
March
26, 1999:Technical Tasks |
April
16, 1999:Technical Task and Accomplishments |
May
21, 1999:Technical Tasks |
May 28, 1999: Most
of the week was spent trouble shooting the rf system, looking
for the jitter that has plagued the ATF for over one week.
|
June
4, 1999: During this short week, we reinstalled the new
YAG oscillator. |
June
11, 1999: The previously owned ac line conditioner was repaired
and tested. |
July
9, 1999: ATF experimental hall modification for VISA was
finished and approved for operation by NSLS safety. |
July
16, 1999: After many days of troubleshooting the rf system,
Marc Montemagno has found major causes of erratic behavior. |
July
23, 1999: The main concern this week was RF stability. The
older high voltage power supply borrowed from SDL was not well regulated
enough for our needs. |
July
30, 1999: This week I completed the temperature stabilizer
prototype for the RF phase/amplitude drivers. |
August
6, 1999: ATF Schedule for September and October: The only
request received so far is from the Compton experiment. |
August
13, 1999: This weeks ATF activities concentrated on the
preparation of components for the extension of beam line #3. |
August
20, 1999: During the week of HGHG we have experienced multiple
failures in the Darlington power supply system. |
August
27, 1999: This week proved quite interesting! The remaining
low level rf temperature controller was installed in the gun system
and the results were overwhelming. |
September
3, 1999: Technical Tasks |
September 10, 1999:
During this short week we were able to finish all magnet cabling
for the primary VISA beam line.
|
September
17, 1999: This week we were able to complete the VISA #3a
‘test line’ including computerized operation of all
magnets, pop-in’s and diagnostics. |
October
1, 1999: The FD5 magnet transfer switch installed two weeks
ago suffered dearly from rf modulator noise. |
October
8, 1999: The exterior shielding for the VISA beamline was
installed and a radiation fault test was performed. |
October 15, 1999 : This
week was dedicated to shutdown tasks concerning the RF system
and YAG laser area.
|
October
22, 1999: The Joulemeter charging power supply for the YAG
laser system is complete. |
October
29, 1999: On the Monday maintenance day, we anticipated
finding a defective capacitor in the gun modulator. |
November
5, 1999: Due to various illnesses and absentees, this weeks
workload was not as productive as anticipated. |
November
12, 1999: During this short week, we were able to complete
two of the stripline monitor circuit boards for the VISA Experiment.
|
November
19, 1999: Monday was the start of the experiment hall shutdown.
During this time we provided technical assistance to the Russian
BPM experiment in the 0* line including operations and tech support.
|
December
3, 1999: The construction of the VISA stripline monitors
has been completed. |
December
10, 1999: Part of the week was dedicated to repair and assistance
for the experimental program. |
December
17, 1999: As the new year approaches, the list of things
to do in 1999 are dwindling quickly. |
|
|
June
4, 1999: Tuesday: Marcus , Bob and Igor installed the oscillator
and realigned the optics. |
June
11, 1999: The planned Monday beam study was not done due
to a lost lens shipment |
July
9, 1999: A laser mask for locating the electron beam on
the center of the cathode was prepared,
installed and tested. |
July
16, 1999: This week we ran 3 days STELLA. Beam quality was
good. |
September
3, 1999: We had VISA beam line safety walk-through, and
several items come to our attention. |
September
10, 1999: We have corrected the items pointed out by the
NSLS Beam Line Safety Committee walk through for VISA beam line.
|
|