| |
|
Feb-March
2002: To get a short CO2 pulse, we plan to use the YAG laser
and a Kerr switch to slice the long CO2 pulse, and a pulse length
shorter than 5 ps is required. |
|
October
2001: During the last shutdown period (10/22-10/27), significant
effort was made in understanding the limitations encountered when
using so called "Gaussian" or graded reflectivity mirrors
(GRM), for transverse profile shaping in the system. |
|
January
21, 2000: Pulse shortening by saturable absorber: Testing
of the saturable absorber shows good results so far. |
February
18, 2000: This week the testing of the new laser oscillator
confirmed last weeks results that showed unacceptable phase, pointing,
and power stability from the unit. |
March
24, 2000: Last week after the failure of the Pockels cell
driver, it was decided we could use the time while the driver was
under repair to start some laser work needed to improve stability. |
March
31, 2000: This week the laser operated five days for experiments,
with only a couple of hours required on Thursday for CW realignment
to restore good amplitude stability. |
April
14, 2000: Monday urgent realignment of the demo oscillator
was performed to restore optimum mode locking, phase stability,
and output power. |
April
21, 2000: The maintenance this Monday involved several miscellaneous
tasks that had been accumulating for several weeks... |
November
20, 2000: Work on the YAG system over the past few weeks
has been primarily to improve amplitude stability on the cathode. |
|
March
12, 1999: Operated >12 hours 3/6 + 3/7 for STELLA runs
without realignment |
March
19, 1999: 3/12: A quick study of laser beam exiting the
gun was performed by collecting the light at the exit port and directing
it to the streak camera in the gun hutch. |
March
26, 1999: Over the previous weekend the YAG oscillator shut
down on internal interlock. |
April
16, 1999: A system of 11 thermocouple was installed to monitor
the temperature in a few locations in the Yag room. |
May
14, 1999: Last weekend work continued on beam studies and
cathode cleaning was performed Friday. Sunday the laser was operated
for pulse duration measurements. |
May
21, 1999: Some time was devoted to understanding and improving
amplitude jitter of the system. |
June
4, 1999: The new YAG oscillator is back after exhibition
at CLEO 99. |
June
11, 1999: Good laser stability this week allowed reliable
and productive delivery of beam to the gun. |
July
9, 1999: During the shutdown to install the new oscillator,
the oscillator enclosure has been expanded to allow kinematic exchange
of the new and old oscillators with minimal disruption to the optics. |
July
16, 1999: There is little to report this week because of
very successful experimental runs. The laser reliability was very
good for both the STELLA and HGHG runs. |
July
23, 1999: Two days this week were devoted to laser work.
Monday the alignment of the UV beam to the cathode was checked.
|
August
6, 1999: Tuesday and Wednesday were devoted to maintenance.
The Pockels cell installed last week with the new high voltage pulser
for double pulse operation was optically damaged. |
August
13, 1999: The laser provided beam all week without maintenance
and only minor realignment to the cathode, and oscillator power
was stable within 2%. |
October
22, 1999: The RF master oscillator supply was relocated
to a new rack in the laser lab where the heat loading should not
affect the YAG laser. |
| October
29 1999: There was laser maintenance on Monday during which
the amplitude instability from ground motion was further studied.
|
November
5, 1999: This Monday’s scheduled laser maintenance
was realigned of the oscillator, again because of degradation of
the saturable absorber. |
November
12, 1999: The maintenance day on Monday was used to set
up some tests of the saturable absorber which could potentially
be used to shorten the IR pulse duration. |
December
10, 1999: Monday maintenance consisted of some mechanical
work on interlock shutters, and, prompted by the BPM experiment
results, another measurement to search for multiple pulses at the
gun. |
|
|
February
23, 2005: Since the last status report of the ATF CO2
laser in the ATF Newsletter of February 2004, much progress has
been made toward bringing the CO2 laser in line with the increasingly
challenging demands of ATF user experiments on advanced laser acceleration
(STELLA LWFA, LACARA) and radiation sources (Thomson scattering,
EUV). |
|
February
2004: Our CO2 laser, being synchronized to the ATF linac,
enables laser/e-beam interaction experiments. A number of such user’s
experiments have been successfully completed over the past years. |
|
Jan.-March
2003: The upgrade of the ATF CO2 laser system to a few-picosecond
pulse at Terawatt peak power is a the final stage. |
|
April-June
2002: In order to achieve terawatt peak powers with the
ATF CO2 laser, it is necessary to reduce the pulse duration to a
few picoseconds before seeding the amplifiers. |
Oct.-Dec.2002:
The testing of the CO2 short pulse upgrade is now beginning.
Optics for delivering the YAG pulses to the CO2 room are in place,
and have been aligned using a green HeNe laser. |
|
September
2001: The ATF continues with the upgrade of the facility,
in particular its high-power CO2 laser, in order to better serve
the more demanding users' experiments. |
|
February
4, 2000: In the continuing work towards the operation of
the terawatt laser, the gigawatt pulse generated by the ATF CO2
laser was trimmed from FWHM 200 ps to 25-30 ps using a combination
of a plasma shutter and a saturable absorber. |
December
28, 2000: The ATF terawatt CO2 laser is not in service yet.
However, a festive moment expected by the ATF users is approaching. |
| |
March
12, 1999: The acceptance test of the Terawatt CO2 laser
amplifier built by OPTOEL Co. (Russia) has been completed this week. |
May
21, 1999: Two-stage semiconductor optical system is reestablished
and tested. |
May
28, 1999: Optics installed to deliver the alignment and
amplified CO2 laser beams to the auto-correlator to measure the
duration of the amplified pulse. |
June
4, 1999: Installation of beam enclosures for the CO2 laser
transport line between rooms C1 and C2 and work on eliminating gas
leaks in the CO2 laser preamplifier and in the terawatt amplifier
are still in progress. |