|
|
| February:
Chicane centerpiece diagnostic was installed and tested. Beam
image was obtained in the middle of chicane. |
|
| January-March:
VISA II will perform an experimental study of the physics
of a chirped beam, SASE FEL using the upgraded facilities at the
ATF. |
| April-May:
In this period VISA achieved the first sustainable lasing after
the renewal of the effort. Here is the summary of the results.
|
|
| October-December:
After compression, linear transport through final bending
systems has also been found (notably in the first round of VISA
experiments), to have dramatic effects on the final beam phase space,
and thus the SASE process. |
|
| January
2001 : The last few weeks have been dedicated to moving
the undulator (while in vacuum) to the correct position and a continuation
of running the VISA system. |
| February
2001: We’ve had 5 run days this last block. Heinz-Dieter
arrived last Wednesday and stayed through our runs this week.
|
| March
2001: On behalf of the VISA collaboration, we are very pleased
to announce that VISA has recently demonstrated a gain of 2x10^6,
and an exponential growth rate (intensity gain length) of 18.5 cm. |
| April
2001:During the last several run weeks energy vs. distance
measurements were done after the system was peaked up. |
| May
2001: Last week was the VISA meeting here at BNL. The talks
went well. |
| August
2001: The VISA collaboration finished its last experiment
run in the first week of June. |
|
| January
14, 2000 : On Tuesday, we propagated beam to Pop-in 1 which
is just a silicon mirror without use of the BPM optic design. |
| January
21, 2000: A Molectron detector was set up at the FEL mirror
of Pop-in 8. |
| January
28, 2000: We are currently preparing for the last run days
before the shutdown. |
| February
4, 2000: We saw good OTR signal through the BPM using the
more sensitive COHU camera. |
| February
25, 2000: Robert and his team came out and did an alignment
using the laser interferometer this last holiday weekend. |
| March
10, 2000: We slowly pumped down the system and the vacuum
looks good. |
| March
24, 2000: We were able to transport 100% of the beam (700pC)
@ 71MeV with no corrector steering. |
| April
14, 2000: Last Friday’s run We did radiation vs. charge
and it is still linear. |
| April
21, 2000: For our next two run days, we are going to solely
study the trajectory and how to improve it by correction algorithms
using the two upstream steering magnets. |
| May
5, 2000: XJ started at 9 am with laser profile and e-beam
profile studies in the tunnel because there was observed structure
in the e-beam profile. |
| May
19, 2000: These last two weeks were shutdown for VISA. |
| June
9, 2000: For PAST couple of months, Alex has been working
on the upgrade of BPM optics, and alignment laser systems. Last
run was a “beta”-test for both. |
| July
26, 2000: Data taken from the last runs indicate little
correlation to the proposed correct trajectories sent out by Robert.
|
| November
20, 2000: The big VISA shutdown has been completed and we
are working our way towards a run. |
| December
28, 2000: After the shutdown was completed, we started running
the VISA system again. Similar to last time, trajectory studies
in the horizontal and vertical were measured. |
|
| March
12, 1999: Undulator Sections #2 and #3 were individually
set up on the pulsed wire bench in the normal (upright) orientation
for tuning. |
| March
19, 1999: Magnetic shimming of Undulator Section #4 was
completed. |
| April
16, 1999: Undulator Sections #2 and #3 were checked on the
pulsed wire bench. |
| May
14, 1999: The leveling of the undulator support stands has
been machined and the redheads for the stands have been installed
in the experimental hall. |
| May
21, 1999: There was a delay with the machining of the jig
support plates and the pre-assembly for VISA will begin the week
of May 31 in Building 726. |
| May
28, 1999: Ben Poling and Roger Carr will arrive at BNL next
Tuesday evening, and work next Wednesday, Thursday, and Friday to
re-assemble VISA, with the newly machined pedestals and table tops.
|
| June
4, 1999: Three crates of Robert Ruland’s alignment
materials have arrived. Holes in the top plates for the alignment
fixtures that were misdrilled will be corrected. |
| July
23, 1999: George is continuing with the final undulator
characterization and hopes to be done by next week. |
| July
30, 1999: On Monday, one more set of interferometry measurements
was done on Sections #1 and #2 in the 90 and 270 degree orientations. |
| August
6, 1999: We need a new chiller for the 30 A power supplies
required for VISA. Due to the fact that the ATF ran out of funding
for FY99, a serious delay is expected in full energy VISA operations. |
| August
13, 1999: The undulator will be shipped back to SLAC to
have the tooling balls fixed. Approximate delivery time is August
23rd. |
| August
20, 1999: The second alignment diode laser has been ordered.
It operates at 660 nm, output power 10 mW. |
| August
27, 1999: The status of the undulator segments is that they
are at SLAC, the tooling balls have been purchased and have had
holes put into them. |
| September
3, 1999: August 30 Complete CMM measurements of undulator
sections at SLAC and ship to BNL. |
| September
10, 1999: The undulator tooling fixtures took a little longer
than originally expected. |
| September
17, 1999: The test beamline (ATF beamline #3) was run this
week. |
| October
1, 1999: Last Monday, Alex and Vitaly conducted an experiment
to test a YAG-crystal applicability as a VISA beam profile monitor. |
| October
8, 1999: Vacuum testing on the vacuum chamber is in progress.
A low temperature bake was done and a small leak was found in one
of the o-rings and fixed. |
| October
22, 1999: The apparently huge (up to 1.2 mm) closure errors
between fiducialization and CMM data were due to an error in a spreadsheet
reference. |
| October
29, 1999: Mirrors (for the diagnostic pop-ins) received
from Opticraft ended up being no good... not even for the electron
beam diagnostic. |
| November
5, 1999: A valve can be installed before the VISA undulator
which will isolate VISA from the rest of the experimental hall beamlines. |
| November
12, 1999: The BPM was installed last Wednesday, and vacuum
at VISA beam line this morning is 7x10^(-8). |
| November
19, 1999: Ben arrived and the vacuum chamber has been installed
in the ATF and rough surveyed into place. |
| December
3, 1999: This week Robert and the alignment team are here
and setting up the laser interferometer. |
| December
10, 1999: Robert and his team finished the alignment Tuesday
morning. It was estimated that the alignment was peak to peak 100um
over the 4m. |
| December
17, 1999: This week we finalized the chamber and upstream
beamline and bolted up. |