#97-100
Issued 10/6/97
Status of Environmental Management Activities
At Brookhaven National Laboratory
Upton, NY Officials at the U.S. Department of Energy's Brookhaven National
Laboratory met today with representatives of regional regulatory agencies,
elected officials and community groups to provide an update of environmental
management efforts at BNL.
BNL initiated a site-wide review of its facilities in April of this year
and issued an interim report on September 10, 1997. Environmental concerns
reported in September were subdivided into two broad categories: "Underground
Sumps, Tanks, Lines and Ducts" and "Historic Discharges of Solvents,
Oil, and Mercury."
During the course of the comprehensive review, the Lab immediately corrected
a number of deficiencies. Since the interim report was issued, BNL has taken
aggressive further follow-up action.
One follow-up action dealt with the ongoing investigation of the Brookhaven
Graphite Research Reactor complex. The partially decommissioned graphite
reactor operated from 1950-1968. The reactor complex has an empty spent-fuel
pool, an inactive underground sumps, tanks and air ducts, all known to be
contaminated with radioactivity.
On September 15 of this year, BNL found standing water in a vertical pipe
connected to an air duct used to cool the reactor. On further inspection,
the Lab found that the below-ground portion of the air duct contained an
estimated 60,000 gallons of water. Sampling and analyses indicate that the
water is contaminated with radionuclides, including strontium-90, cesium-137
and tritium.
BNL expects to begin pumping water out of the air duct soon. This process
will take several weeks. The water will be temporarily stored in tanks with
secondary containment in a paved, curbed and isolated area on the Lab site
until it can be processed and/or removed from the property.
The Lab established a committee to determine the source of the water in
the air duct. Past leakage from cooling coils and rainwater intrusion are
the two most likely sources. The cooling coils have been isolated, and BNL
is evaluating methods to prevent rainwater from getting into the duct.
The following chart shows the radionuclides of concern in the air duct.
| Radionuclide | Concentration in Duct* |
| strontium-90 | 10 million pCi/L |
| cesium-137 | 4 million pCi/L |
| tritium | 50 thousand pCi/L |
· On September 16, BNL pumped out 600 gallons
of liquid and sludge from an underground tank in Building 525. The material,
contaminated with radionuclides, will be processed on site and sent for
disposal off site. The tank is scheduled to be removed by the end of the
year. Groundwater downgradient from the tank was sampled in August, and
all analyses have not been completed.
· On September 30, mercury and mercury-contaminated soil were removed
from a crawl space underneath a former laboratory in Building 197. Sampling
will be done by mid-October to determine if any further remediation is required.
The area was surveyed for mercury vapor in May, when the original inspection
was done, and no mercury vapor hazard exists to employees in the workplace,
as all readings were at background levels.
· Building 830 houses two large shielded rooms in which radionuclides
were handled. The rooms are connected by a water-filled canal to transfer
sealed radioactive sources between the rooms. BNL has completed both a safety
review
for pumping out water from the canal and a leak test. The leak test indicated
that the canal is leaking about five gallons a day. Analyses of the canal
water, however, indicate that it meets the drinking water standard for radionuclides.
Additionally, groundwater samples in the immediate vicinity of the building
show radionuclides well below the standard. The canal is scheduled to be
pumped out by mid-October.
Three actions originally scheduled to be completed by the end of September
will completed during October. About 100 gallons of water must be pumped
out of a sump in Building 701, a water-level indicator must be installed
in a vertical pipe at Building 704, and underground waste lines need to
be checked at Building 801.
30