Time line:
|
Cool down before gun modification, measure Q,
heat loss and vacuum pressure.
|
February 08
|
|
Modify gun, install cathode plug receiver
|
May 08
|
|
Gun cleaning
|
June 08
|
|
Construction of a cave from concrete blocks for
radiation protection
|
September 08
|
|
Cool down without cathode plug, measure Q as
function of gradient.
|
September 08
|
|
Cool down with cathode plug and uncesiated GaAs
cathode, no laser.
|
October 08
|
|
Purchase transporter system
|
October 08
|
|
Assemble preparation chamber with heater,
cesiation system and quantum efficiency measurement
|
November 08
|
|
Test with cesiated GaAs cathode and
laser
|
January 09
|