Attendees : D. Davino, A. Fedotov, H. Hahn, Y. Y. Lee, N. Malisky, S. Tepikian, N. Tsoupas, D. Raparia, G. Parzen
The need of electrical vacuum break was discussed and decided that there is no need of it in the ring.
The Location of ground break in HEBT, Ring and RTBT were presented by R. Lambiase.
R. Lambiase will also follow up on what transformer feed what.
Raparia presented the new collimator aperture and locations in the RTBT
to make the acceptance of these collimator similar to the vacuum window in the target region
namely 300 pi in horizontal and 400 pi in vertical plane.
Tepikian presented the progress on the survey coordinate for the ring and compared with old ones.
N. Tsoupas present the design progress on the Injection magnet
D. Davino discussed the impedance of the off center beam in the kickers