The Laboratory currently has six treatment systems on and off site operating 24 hours a day to clean up groundwater. The following is an update of groundwater treated and amount of contaminants removed.

Operable Unit I South Boundary Pump-and-Treat System - formerly RA V (operating since 12/96):

Operable Unit III Pump-and-Treat System (operating since 6/97):

Tritium Remediation System (operating since 5/97)

Operable Unit IV Air Sparging/Soil Vapor Extraction System (operating since 11/97)

Operable Unit III Off-site In-Well Air Stripping System (operating since 9/99)

Carbon Tetrachloride Groundwater Removal Action System (operating since 10/99)

To date, more than 1.7 billion gallons of groundwater have been treated, and more than 1,200 pounds of contaminants have been removed from the sole source aquifer.

 