| Brookhaven National Laboratory | |||||||||||||
| Pollution Prevention Program Current Year Work Plan (FY08) | |||||||||||||
| Task Type | Task | Primary Responsibility | Secondary Responsibility | Due Date | Status | Details | Links | ||||||
| ROI projects | Call for proposals | P. Pohlot | P2 Council, ECRs, EWMSD | Nov. 2007 | complete | Distributed call for proposals in Monday Morning Memo on 9/24/07 | FY08 Call for Proposals | ||||||
| ROI projects | Directorates submit P2 Proposals to the P2 Council for evaluation of applicability and viability | P. Pohlot | Oct. 22, 2008 | complete | Proposals were accepted up through April | ||||||||
| ROI projects | Place ROI proposals on P2 webpage for review and ranking by P2 Council | P. Pohlot | Dec., 2007 | complete | Listed proposal titles on P2 Funding Opportunities webpage and hotlinked MSWord proposal forms as obtained | P2 Funding Opportunities | |||||||
| ROI projects | Prepare ranking spreadsheet and distribute to P2 Council | P. Pohlot | Jan., 2008 | complete | Excel spreadsheet lists all proposals, and provides ranking instructions for each directorate to score proposals. Funding of $20,000 released mid-April. Ranking spreadsheet sent out on 4/17/08 | ||||||||
| ROI projects | Rank P2 proposals | P2 Council | P. Pohlot | Jan. 2008 | complete | Rank list and return to P. Pohlot - final rankings tabulated on 4/29/08 | |||||||
| ROI projects | Calculate ranking, set up project activity codes with J. Ramirez, draft and distribute memos | P. Pohlot | J. Ramirez | Jan. 30, 2008 | complete | Memo's sent out 4/30/08 to successful proposers | |||||||
| ROI projects | Call for Status Update | P. Pohlot | P2 Council, ECRs | June 30, 2008 | Issue request for status of project implementation, in last quarter request success story documentation | ||||||||
| Sept. 30, 2008 | |||||||||||||
| ROI projects | Status Update | Project Sponsors | P. Pohlot | July 15, 2008 | Project sponsors provide status of cost and schedule for project implementation | ||||||||
| Sept. 1, 2008 | |||||||||||||
| ROI projects | Document success story | Project Sponsors | P. Pohlot | Aug. 1, 2008 | Project sponsors or designee document success story on P2 webpage form | On-line Success Story Form | |||||||
| Reporting | Annual Report on Waste Generation and Pollution Prevention Progress for '07 | G. Todzia | P. Pohlot | Dec. 31, 2007 | complete | DOE annual report, requires recycling amounts, and waste generation - 12/22/07 | |||||||
| Reporting | Affirmative Procurement Report | A. Bou | PPM, Plant Engineering, Staff Services | Dec. 31, 2007 | complete | Report annually on procurement of EPA designated recycled content items purchased - 12/22/07. | |||||||
| Reporting | Site Environmental Report, Charts of routine rad, mixed, and haz waste generation | G. Todzia | J. Selva | June 30, 2008 | Obtain routine waste generation numbers from G. Todzia and add to running chart that tracks performance since 1992 | ||||||||
| Reporting | Site Environmental Report, Text for Pollution Prevention Section | P. Pohlot | G. Todzia | April 30, 2008 | in progress | Rewrite P2 Section of SER. | |||||||
| Reporting | Hazardous Waste Reduction Plan | G. Todzia | S. Ferrone | June 30, 2008 | Required to be submitted to NYSDEC every year | ||||||||
| Administration | P2 Council | P. Pohlot | G. Todzia | on-going | Organize meetings, distribute agenda, engage Council in projects - P2 Council reviewed the white paper on Future P2 Funding Options | BNL Pollution Prevention Council charter | |||||||
| Administration | Update and maintain Pollution Prevention Subject Area | P. Pohlot | Team | May 31, 2011 | Full update required every 5 years, regular update when requirements change - last update was 5/31/06 | P2 Subject Area | |||||||
| Administration | P2E2 Goals and Resource Commitments to Achieve Secretarial Goals | P. Pohlot | G. Todzia, M. Toscano, J. Swenson, J. Williams | Periodically | Required by DOE in FY01, involved establishing goals and budget estimates for P2, energy efficiency, and transportation projects. Periodically monitor progress. | ||||||||
| Administration | Establish CYWP | P. Pohlot | Dec. 2008 | complete | |||||||||
| Administration | P2 Web Page update and maintenance | P. Pohlot | on-going | Update with new ROI proposals, what's new, conference information, rank and tracking spreadsheets, recycling statistics, etc | BNL P2 Webpage | ||||||||
| Administration | P2 Performance Measures | G. Goode | G. Todzia, P2 Council | July-Sept | Working with Brookhaven Group, develop set of P2 performance measures | ||||||||
| Tracking | Track performance against measures | P. Pohlot | G. Todzia | Periodically | Report performance through established mechanisms (self assessment plan, etc) | ||||||||
| Tracking | Develop CY Tracking Spreadsheet for SER | P. Pohlot | G. Todzia | May 30, 2008 | Excel spreadsheet lists all P2 projects and recycling operations and provides cost saving information | P2 Tracking Sheet | |||||||
| Tracking | Waste Generation graphs for SER | G. Todzia | J. Selva | Mar. 31, 2008 | Excel spreadsheet that tracks rad, mixed and haz waste generation since 1993 in bar graph format. | ||||||||
| Awards | DOE Awards Program, solicit nominations through P2 Council, ECRs | P. Pohlot | ECR's, Line Supervisors | Dec. 31, 2007 | complete | Submitted with annual P2 Report on 12/22/07 | |||||||
| Awards | Earth Day Awards, solicit nominations through P2 Council, ESD | Earth Day Coordinator | P2 Council Line Supervisors, ECR's | Mar. - Apr. 2008 | complete | Earth Week held April 21-25, 2008 | |||||||
| Awards | Earth Day Awards, prepare certificates, prizes for distribution at Earth Day | Earth Day Coordinator | Mar. - Apr. 2008 | complete | Earth Week held April 21-25, 2008 | Earth Day website | |||||||
| Awareness | Bulletin Article on ROI Projects | Public Affairs | P. Pohlot | July 30, 2008 | |||||||||
| Awareness | Publicize DOE Awards | Public Affairs | P. Pohlot | June 30, 2008 | Date dependant on DOE Conf. | ||||||||