1.0 SMD Documents
1.2 Procedures 3 9/18/2008
2.0 Guidelines for the Conduct of Operations
2.1 Training and Qualification 2 1/1/2007
2.2 Operation of the ESH&Q Office for the SuperConducting Magnet Division 5 6/16/2005
2.12 Work Planning and Control 4 10/8/2008
3.0 SuperConducting Magnet Division Emergency Procedures
3.0 Local Emergency Plan for the SuperConducting Magnet Division 3 8/15/2007
8.0 Magnet System
8.1 Operation of 12T Coil Collaring Press, P/N 25-1925.01-5 0 10/27/2005
8.1.1.1 Operation of Long Coil Winder Inactive
8.1.1.3 Operation of 8.5kA Power Supply for Vertical Magnet Testing 2 10/21/2008
8.1.1.4 Operation of the Twin 15 kA Power Supplies for Short Sample Testing 2 8/24/2005
8.1.1.5 Operation of Collaring Press Inactive
8.1.1.7 Test of Safety Interlocks of the Short Sample Test Facility, Twin 14 kA Power Supplies 1 8/25/2005
8.1.1.8 Operation of the Superconducting Cable Insulating Line Inactive
8.1.1.9 Test of Safety Interlocks of MAGCOOL 10 kA Power Supply Inactive
8.1.1.10 Test of Safety Interlocks of Trim Power Supplies for Horizontal Magnet Testing Inactive
8.1.1.11 Switch Over from Auxiliary Crane Hoist to Lodestar Chain Hoist Inactive
8.1.1.12 Safety Communication Procedure for Non-Magnet Test Group Personnel Entering Red Fenced Areas 2 10/27/2005
8.1.1.13 Calibration of Main Hydraulic Pressure Measurement System on Collaring Press Inactive
8.1.1.16 Operation of Corrector Coil Overwrap Machine Inactive
8.1.1.19 Operation of Short Coil Winder Inactive
8.1.1.20 Operation of MAGCOOL 10 kA Power Supply for Horizontal Magnet Testing 2 9/8/2005
8.1.1.21 Operation of Trim Power Supplies for Horizontal Magnet Testing Inactive
8.1.1.22 Operation of Bus Soldering Line 5 9/28/2006
8.1.1.23 Operation of CQS Shell Welder Inactive
8.1.1.25 Operation of Northrop/Grumman Wrapping Machine 2 3/15/2006
8.1.1.26 Operation of Wedge Wrapper Inactive
8.1.1.27 Operation of Beam Tube Wrapper 2 3/15/2006
8.1.1.28 Operation of Automated Long Curing Press Inactive
8.1.1.29 Operation of Short Coil Curing Press Inactive
8.1.1.30 Operation of Dual Acme Power Supplies 1 9/12/2005
8.1.1.31 Test of Safety Interlocks of Dual Acme Power Supplies 1 9/12/2005
8.1.1.32 Operation of Direct Wind Wrapper 1 11/15/2005
8.1.1.33 Operation of the Beam Tube Curing Oven 2 10/31/2005
8.1.1.34 2M Direct Wiring Machine 1 9/12/2005
8.1.1.35 Test of Safety Interlocks of 8.5kA Power Supply 1 9/1/2005
8.1.1.36 3M Direct Wiring Machine 1 9/12/2005
8.1.1.37 Operation of the NGC Long Coil Winder Inactive
8.1.1.38 Operation of the NGC Long Coil Curing/Collaring Press Inactive
8.1.1.39 Operation of the LHC Shell Welding Fixture Inactive
8.1.1.41 Test of Safety Interlocks for the Short Sample Test Facility, Magnet Power Supply 0 8/25/2005
8.1.1.42 Test of Safety Interlocks of the 5kA Axion Power Supply 3 5/9/2007
8.1.1.43 Operation of Universal Coil Winder 1 10/27/2006
8.1.1.44 Generic LOTO Procedure Incorporating UPA-100 LED Meter and AC Panel Meters 0 5/13/2005
8.1.1.45 Operation of the LARP Coil Spooler 0 11/13/2006
8.1.1.46 Operation of the Long Coil Oven 0 5/30/2007
8.1.3 Cryogenic System
8.1.3.1 Operation of MYCOM Compressor for MAGCOOL Refrigerator 2 3/8/2007
8.1.3.3 Operation of DUNHAM-BUSH Compressor for "PAT" Refrigerator inactive
8.1.3.5 Operation of Three 100 HP SULLAIR Compressor for MAGCOOL 2 3/8/2007
8.1.3.7 Operation of the MAGCOOL System 2 3/8/2007
8.1.3.8 Operation of the MAGCOOL Pump and Purge System 2 3/8/2007
8.1.3.9 Operation of MAGCOOL Helium Purifiers 2 3/8/2007
8.1.3.10 Operation of Cooldown #1 System 2 3/8/2007
8.1.3.11 Operation of Cooldown #2 System 2 3/8/2007
8.1.3.12 Operation of the MAGCOOL Test and Measure System for Bay D and E 2 3/8/2007
8.1.3.13 Operation of Model 4000 Refrigerator (MAGCOOL Refrigerator) 2 3/8/2007
8.1.3.14 Operation of the Warmup System 2 3/8/2007
8.1.3.15 Operation of the MAGCOOL CRT 2 3/8/2007
8.1.3.16 Operaton of Nash Refrigeration Pumps 1 4/18/2005
8.1.3.17 Cryogenic Operation of Test Dewar #2 2 3/8/2007
8.1.3.18 Cryogenic Operationof Test Dewar #3 1 4/23/2005
8.1.3.19 Cryogenic Operation of Cable Test Dewar #4 1 9/16/2005
8.1.3.20 Cryogenic Operation of Cable Test Dewar #5 1 9/16/2005
8.1.3.21 Cryogenic Operationof Cable Test Dewar #6 1 9/16/2005
8.1.3.22 Operation of the MAGCOOL Test and Measure System for Bay C 1 8/14/2007
8.1.3.23 Cryogenic Operation of AGS Cold Snake Magnet in B902 inactive