Wednesday, February 1, 2012  Building 817, Room 4

08:00 - 08:30 Executive Session Committee
08:30 - 08:45 Welcome Steve Dierker
08:45 - 09:25 Accelerator Overview Ferdinand Willeke
09:25 - 09:55 Power Supply and Power Distribution Systems Status Wing Louie
09:55 - 10:10 Break  
10:10 - 10:30 Magnet Production  Satoshi Ozaki
10:30 - 10:55 RF Systems Status Jim Rose
10:55 - 11:20 Vacuum Systems Status H.-C. Hseuh
11:20 - 11:40 Instrumentation Status Dan Padrazo
11:40 - 12:00 X-Ray Diagnostics Peter Ilinski
12:00 - 12:15 Discussion All
12:15 - 13:10 Lunch Break  
13:10 - 14:25 Tour  
14:25 - 14:50 Accelerator Physics Progress  Sam Krinsky
14:50 - 15:20 Injector Status Timur Shaftan
15:20 - 15:40 Magnet-Girder Integration Lewis Doom
15:40 - 15:55 Break  
15:55 - 16:25 Installation and Integrated Testing Status and Plans Greg Fries
16:25 - 16:45 Control System Progress Leo Dalesio
16:45 - 17:05 Reserve for discussion and additional information  
17:05 - 19:05 Executive Session
19:05 Dinner  

Thursday, February 2, 2012  Bldg. 817, Room 4

08:30 - 09:00 Insertion Device Status Toshi Tanabe
09:00 - 09:30 Planning for NSLS-II Commissioning and Operations Ferdinand Willeke
09:30 - 12:00 Executive Session  
12:00 - 13:00 Lunch  
13:00 - 14:00 Closeout  
14:00 Adjourn  

 

 

Recent Project Reviews  (note: Reports are posted at the top of each review site.)

Recent NSLS-II Monthly Project Reports  

Installation and Commissioning

Top of Page

Last Modified: May 2, 2014
Please forward all questions about this site to: BNL Web Services