NSLS-II Project Advisory Committee Meeting
November 20, 2007
Committee Charge
(pdf) | Meeting
Agenda
(pdf) | PDF
Problems?
Committee Report:
NSLS-II Project Advisory
Committee Meeting
(pdf)
Tuesday, November 20
BNL Bldg 817, Room 4 (Large
Conference Room)
| 08:00 – 08:30 |
NSLS-II Overview
(ppt) |
S. Dierker |
| |
Activities, achievements since last PAC
meeting |
|
| |
Response to previous PAC
recommendations |
|
| |
Summary of EIR and IPR recommendations
and responses |
|
| |
Issues and charge |
|
| 08:30 – 09:00 |
NSLS-II Project Baseline
(ppt) |
J. Yeck |
| |
Summary of baseline and issues |
|
| 09:00 – 09:30 |
Conventional Facilities
(ppt) |
M. Fallier |
| |
Organization, staffing, construction approach, procurements,
schedule, outstanding design issues |
|
| 09:30 – 10:00 |
Accelerator Systems
(ppt) |
F. Willeke |
| |
Organization, staffing, construction approach, procurements,
schedule, controls, and spares, outstanding design issues |
|
| 10:00 – 10:15 |
Break |
|
| 10:15 – 10:45 |
Experimental Facilities
(ppt) |
J. Hill |
| |
Construction approach (use of vendors, etc), outstanding design
issues |
|
| 10:45 – 12:00 |
Discussion on construction approach |
J. Yeck, et al. |
| |
Includes teleconference with IPR team members F. Kornegay and M.
Reichanadter on ES&H and Conventional Construction |
|
| 12:00 – 01:00 |
Lunch and Executive Session |
|
| 01:00 – 02:00 |
Strategy for Beamline Development
(ppt) |
J. Hill |
| |
User Access and Beamline Development Policies, Beamline Advisory
Teams, Major Item of Equipment (MIE) Funding, Life Sciences,
Engagement of User Community, Scientific Strategic Planning;
Includes teleconference with S. Mochrie, Chair of NSLS-II
EFAC |
|
| 02:00 – 03:00 |
Additional Discussion |
|
| |
Potential topics:
Procurement
(ppt),
HR
(ppt), Interfaces,
other |
|
| 03:00 – 03:15 |
Break |
|
| 03:15 – 04:45 |
Executive Session |
|
| 04:45 – 05:15 |
Closeout |
|
Last Modified: September 28, 2008 Please forward all questions about this site to:
Gary
Schroeder
|