NSLS-II Project Schedule
 

Major Milestone Event
Major Milestone Event Preliminary Schedule
CD-0 (approve Mission Need) 4th quarter, FY2005
CD-1 (approve Alternative Selection and Cost Range) 4th quarter, FY2007
CD-2 (approve Performance Baseline) 1st quarter, FY2008
CD-3 (approve Start of Construction) 2nd quarter, FY2009
CD-4 (approve Start of Operations) FY2015

 