 ECN 01 Final.pdf 555073 2/17/2010 5:31:17 PM PDF File
 ECN 02 Final.pdf 139175 2/17/2010 5:31:17 PM PDF File
 ECN 03 Final.pdf 326592 2/17/2010 5:31:17 PM PDF File
 ECN 04 Final.pdf 256576 2/17/2010 5:31:17 PM PDF File
 ECN 05 Final.pdf 144595 2/17/2010 5:31:18 PM PDF File
 ECN 06 Final.pdf 139731 2/17/2010 5:31:18 PM PDF File
 ECN 07 Final.pdf 1479818 2/17/2010 5:31:18 PM PDF File
 ECN 08 Final.pdf 141035 2/17/2010 5:31:18 PM PDF File
 ECN 09 Final.pdf 723136 2/17/2010 5:31:18 PM PDF File
 ECN 10 Chemical Feed Injection.pdf 802270 2/17/2010 5:31:18 PM PDF File
 ECN 11 Piping Sleeves.pdf 811174 2/17/2010 5:31:19 PM PDF File
 ECN 12 Final - Metal Deck.pdf 674452 2/17/2010 5:31:19 PM PDF File
 ECN 13 TE-4 Function and Control Sequence.pdf 1132715 2/17/2010 5:31:19 PM PDF File
 ECN 14 Sanitary Cooling Tower Overflow Pipe.pdf 661057 2/17/2010 5:31:19 PM PDF File
 ECN 15 Knock Out Wall Detail.pdf 277724 2/17/2010 5:31:20 PM PDF File
 ECN 16.pdf 1874340 2/17/2010 5:31:20 PM PDF File
 ECN 16A Cooling Tower Grounding and Duct Banks.pdf 911100 7/8/2010 4:19:53 PM PDF File
 ECN 17 Metal Panel Thickness.pdf 292866 2/17/2010 5:31:20 PM PDF File
 ECN 18 Sanitary Piping.pdf 735246 2/17/2010 5:31:20 PM PDF File
 ECN 19 Load Tap Changer.pdf 187263 2/17/2010 5:31:21 PM PDF File
 ECN 20 - Steam and Condensate Piping.pdf 2455161 2/17/2010 5:31:21 PM PDF File
 ECN 21 - Mezzanine Floor Framing Detail.pdf 596287 2/17/2010 5:31:21 PM PDF File
 ECN 22 - Exposed Duct Bank Bent Plate.pdf 364912 2/17/2010 5:31:21 PM PDF File
 ECN 23 Grounding in Operating Floor Slab.pdf 555926 2/17/2010 5:31:21 PM PDF File
 ECN 24 Bldg 600A Underground Piping.pdf 554081 2/17/2010 5:31:22 PM PDF File
 ECN 25 - Tunnel Sump Pit Steel.pdf 339951 2/24/2010 3:25:48 PM PDF File
 ECN 26 - Parapet Detail Final.pdf 314349 3/8/2010 3:32:47 PM PDF File
 ECN 27- Bldg 600A Slab Connection.pdf 399458 3/9/2010 5:05:37 PM PDF File
 ECN 28 Parking Lot Layout - Final.pdf 963026 3/16/2010 4:08:27 PM PDF File
 ECN 29 - Electrical Mezzanine Grounding.pdf 475252 3/19/2010 11:39:36 AM PDF File
 ECN 30 Column Wash and Future Pipe Grouting.pdf 1315969 4/7/2010 10:12:57 AM PDF File
 ECN 31 Bus Ratings.pdf 734857 4/7/2010 10:12:57 AM PDF File
 ECN 32 Bldg 600C.pdf 1556224 4/7/2010 10:12:58 AM PDF File
 ECN 32A Cooling Tower Site Plan.pdf 2026635 7/8/2010 4:19:53 PM PDF File
 ECN 32B Bldg 600C.pdf 382165 8/20/2010 9:50:36 AM PDF File
 ECN 32C Bldg 600C.pdf 874457 11/10/2010 4:44:33 PM PDF File
 ECN 33 Electrical Site Plan and Conduit Data.pdf 5021026 4/30/2010 3:15:42 PM PDF File
 ECN 33A Electrical Site Plan and Conduit Details.pdf 2570680 6/22/2010 1:30:22 PM PDF File
 ECN 34 Clarification of Pads and Penetrations.pdf 437182 5/14/2010 3:54:47 PM PDF File
 ECN 35 Transformer No 3 and No 4 Metering.pdf 3897925 5/12/2010 8:23:55 AM PDF File
 ECN 36 Womens Locker Room Faucet.pdf 288480 5/12/2010 4:21:57 PM PDF File
 ECN 37 Thrust Block in Pit.pdf 407124 5/27/2010 3:29:03 PM PDF File
 ECN 38 New Fire Alarm Panel.pdf 1214491 6/22/2010 1:30:23 PM PDF File
 ECN 39 Condenser Water Bleed.pdf 1198916 6/16/2010 10:44:27 AM PDF File
 ECN 40 Specification Section 01340.pdf 177356 6/25/2010 4:16:46 PM PDF File
 ECN 41 Cooling Tower Site Plan.pdf 1486723 7/8/2010 4:19:53 PM PDF File
 ECN 41A - Cooling Tower Site Plan.pdf 656086 3/25/2011 11:38:40 AM PDF File
 ECN 42 SUB-600B and Transformers No 3 and No 4.pdf 1674678 7/16/2010 4:16:15 PM PDF File
 ECN 42A Transformers No 3 and No 4 Fans.pdf 497280 10/20/2010 3:59:00 PM PDF File
 ECN 43 Temporary Enclosure over Cooling Tower Basin.pdf 677151 7/16/2010 4:16:15 PM PDF File
 ECN 44 Control Cable Megger Testing.pdf 157144 7/27/2010 4:29:41 PM PDF File
 ECN 45 Refrigeration Monitoring Panel and SWGR-600-2.pdf 1102549 8/17/2010 4:16:13 PM PDF File
 ECN 45A Refrigeration Monitoring Panel.pdf 1192027 7/29/2011 3:33:55 PM PDF File
 ECN 46 Chiller mtr, pump mtrs, and cooling tower fan mtrs nameplate data.pdf 679196 8/17/2010 4:16:14 PM PDF File
 ECN 47 PANEL RP-U.pdf 414271 8/20/2010 9:50:36 AM PDF File
 ECN 48 - MCC-600-3, EF-6.pdf 299316 8/27/2010 3:17:33 PM PDF File
 ECN 49 - Bldg 600A Louver.pdf 603770 9/1/2010 4:25:33 PM PDF File
 ECN 50 Mounting Plates for Colling Tower.pdf 1013744 9/14/2010 2:38:52 PM PDF File
 ECN 51 Additional Conduits for Power to Future Chillers.pdf 206999 9/14/2010 2:38:52 PM PDF File
 ECN 52 Additional Chiller Pad.pdf 139975 9/14/2010 2:38:52 PM PDF File
 ECN 53 Additional Steel at Coiling Door.pdf 833355 9/14/2010 2:38:52 PM PDF File
 ECN 54 TRNF No 3 and No 4 Alarms and Fan Power Wiring.pdf 3325044 9/28/2010 9:35:30 AM PDF File
 ECN 55 Approved Fuses and CB-Relay settings for delivered equipment-Final.pdf 4254063 11/17/2010 10:45:04 AM PDF File
 ECN 56 - Trane Chiller Remote Starter-Final.pdf 8552682 11/17/2010 10:45:04 AM PDF File
 ECN 56A Trane Chiller Remote Starter.pdf 2886745 4/18/2011 3:20:39 PM PDF File
 ECN 57 Alternate Power RP-U-600 - Final.pdf 305354 11/17/2010 10:45:05 AM PDF File
 ECN 58 Air Compressor Connection.pdf 749167 10/20/2010 3:59:00 PM PDF File
 ECN 59 BLDG 600C Stairs.pdf 313126 11/8/2010 3:36:20 PM PDF File
 ECN 60 - RGDS Tie-In to FACP.pdf 284341 7/29/2011 3:33:56 PM PDF File
 ECN 61 Eliminate SUH-11.pdf 941452 12/3/2010 5:17:04 PM PDF File
 ECN 62 Substation 600-B.pdf 897821 3/18/2011 9:34:23 AM PDF File
 ECN 63 Fire Protection Hose Connection.pdf 316044 1/21/2011 2:55:46 PM PDF File
 ECN 64 Fuses for EF-7 and EF-8.pdf 150906 3/4/2011 4:45:16 PM PDF File
 ECN 65 IPS Piping Class.pdf 404390 2/28/2011 5:18:23 PM PDF File
 ECN 66 Power Transformers Nitrogen System.pdf 416679 2/28/2011 5:18:23 PM PDF File

Please Note:
Acrobat Reader maybe required to view and print some documents.
Get Reader | Can't View PDFs?

Top of Page

Last Modified: February 17, 2010
Please forward all questions about this site to: Richard Scheidet


One of ten national laboratories overseen and primarily funded by the Office of Science of the U.S. Department of Energy (DOE), Brookhaven National Laboratory conducts research in the physical, biomedical, and environmental sciences, as well as in energy technologies and national security. Brookhaven Lab also builds and operates major scientific facilities available to university, industry and government researchers. Brookhaven is operated and managed for DOE's Office of Science by Brookhaven Science Associates, a limited-liability company founded by the Research Foundation for the State University of New York on behalf of Stony Brook University, the largest academic user of Laboratory facilities, and Battelle, a nonprofit, applied science and technology organization.

Privacy and Security Notice  | Contact Web Services for help