By Steve Vigdor
Planning for RHIC Run 9: Although there is still much
uncertainty concerning the federal budget for FY2009, we have to
develop a tentative schedule and plans for the next RHIC run. I
want to bring you up to date on our planning, so that you can
adjust your own plans for completing shutdown work and travel to
BNL accordingly. I’ll also take the opportunity of this column
to inform you about some other recent events concerning RHIC. More...
Shutdown
Maintenance and Operations
By Paul Sampson
Planning and execution of shutdown work in the
Collider-Accelerator Department complex has been reorganized 3
years ago by emphasizing central coordination. The system in
place is modeled after the one used for scheduled maintenance
days during the run, which has shown clear positive results over
the past few years. The system is proving its
value not only in for recording and sharing information on
shutdown activities, but also in increasing the effectiveness
and efficiency of the scheduled work, as exemplified by the
improved smoothness in the transition from shutdown to
operations in the past few runs. With the end of the shutdown
for FY08 nearing and preparation work for the upcoming run in
sight, a review of the ongoing activities is in order.
More...
Users' e-Log
Short news items of interest to the RHIC/AGS community. This week: LHC
Shutdown, RHIC in the LHC Era, and Sorensen Awarded Valley Prize. More...


Construction on the RHIC/ATLAS Computer Facility is under way behind Building 510.