RHIC Spin Collaboration Meeting VI (part 2), November 15, 2001
Small Seminar Room, Physics Dept., Brookhaven National Laboratory
Opening Session
09:00 - 09:15 Summary of RSC Meeting VI Part I / Goals of Part II N. Saito
09:15 - 09:50 Machine Issues for RHIC Spin (Run 3 & Beyond) W. MacKay
(spin rotators/flipper; snake/rotator spares; AGS partial
snake)09:50 10:00 Discussion .. All
10:00 - 10:20 Run 3 Polarization Calibration .. G. Igo
10:20 - 10:40 Run 3 Polarization Calibration .. D. Fields
10:40 - 11:00 Discussion . All
11:00 - 13:00 Lunch
Afternoon Session
13:00 - 13:15 Introduction to Polarization Calibration . Y. Makdisi
13:15 - 14:00 Final Polarization Calibration: Pold Gas Jet T. Wise
14:00 - 14:30 Simulation Studies for Recoil Detectors . E. Stephenson
14:30 - 15:00 Break
15:00 - 15:30 Additional Simulation Studies . S. Bravar
15:30 - 15:45 ep-Polarimeter for RHIC revisted............... F. Meissner
15:45 - 16:30 Discussion G. Bunce
16:30 - 17:00 Summary .. L. Bland
(includes summary of action items from present meeting;
subsequent meeting plans; discussion at future meeting of
future directions of RSC)