LDRD Schedule for Fiscal Year 2017

October 1, 2016 FY 2017 Approval of Funding Ceiling from DOE - SC
October 1 FY 2017 Individual Project Approvals by DOE - BHSO
October 1 - November 15 Populate the OMBE/CFO Database
October 15 Call for FY2016 Annual Reports
November 15 HQ Call for Other Lab-wide Data for Congress
November 20 FY 2016 Individual Project Annual Reports Due to PSP
December 31 Draft FY 2016 Annual Report
January - February 2017 Develop Strategic Plan for LDRD FY2018
March Call for FY2018 Proposals
March 31 FY 2016 Annual Report Due to DOE
June FY 2018 Proposals Due
June - July Annual Review of Projects
July Selection of FY 2018 Projects
August 1 Submit FY 2018 Projects to Laboratory Director for Approval
August 15 FY 2018 Plan Due to DOE
August 31 Submit FY 2018 Projects to DOE for Concurrence