Cost Status: Overview
Management plan completed 4/96, approved 8/96
Last Cost & Schedule review 6/97
Estimated Project Cost now $7.84M (1% increase from 6/97)
Cost to date: $5.01M (64% of EPC)
RHIC funded PO commitments of $982K (13% of EPC)
Contingency of $276K for remaining cost of $1.31M (21%)
Funding source: Polish $1.43M 18% Taiwan .21M RHIC 6.15M 76% NSF .33 $8.13M