Contingency
Value of $276K now at 21% of balance of cost for uncommitted expenses.
Estimates for outside vendors are firm, based on quotations.
Uncertainty in electronics cost essentially in estimate for time to assemble modules and to debug front-end controllers.
Some uncertainty in installation costs.